INSP-Final Inspection | 11/19/2014 | 11/21/2014 | 11/21/2014 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 11/19/2014 | 11/19/2014 | 11/19/2014 | P | PASS |
Troy Cobbley
|
|
|
overhead hydro test passed
|
INSP-Sprinkler Rough-in/Hydro | 11/18/2014 | 11/18/2014 | 11/18/2014 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed.
|
INSP-Sprinkler Rough-in | 10/14/2014 | 10/14/2014 | 10/14/2014 | P | PASS |
Troy Cobbley
|
|
|
tenting passed. piping can be covered.
|
INSP-Sprinkler Rough-in | 10/13/2014 | 10/14/2014 | 10/14/2014 | A | FAIL |
Troy Cobbley
|
|
|
Tenting inspection failed.
|
INSP-Sprinkler Rough-in | 10/13/2014 | 10/13/2014 | 10/13/2014 | P | PART |
Troy Cobbley
|
|
|
Rough-in passed but the tenting inspection failed. Piping can not be covered until the tenting inspection passes.
|
INSP-Sprinkler Rough-in | 8/26/2014 | 8/26/2014 | 8/26/2014 | P | PASS |
Troy Cobbley
|
|
|
Underground ok for cover
|
Issue and Print Permit | | | 8/4/2014 | | DONE |
Tisha Gallop
|
|
|
|
Inspection Record Card- Fire | 8/4/2014 | | 8/4/2014 | | DONE |
Tisha Gallop
|
|
|
|
Plan assigned to (Tim) | 8/1/2014 | | 8/1/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/1/2014 | | 8/1/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 8/1/2014 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/1/2014 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 7/25/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 25 2014 6:45AM
|