INSP-Final Inspection | 1/22/2015 | 1/23/2015 | 1/23/2015 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 1/21/2015 | 1/22/2015 | 1/22/2015 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed
|
INSP-Final Inspection | 1/21/2015 | 1/22/2015 | 1/22/2015 | A | CANC |
Troy Cobbley
|
|
|
Not ready for final due to missing facp
|
INSP-Sprinkler Rough-in/Hydro | 1/21/2015 | 1/21/2015 | 1/21/2015 | P | CANC |
Troy Cobbley
|
|
|
Overhead hydro not ready due to broken pipe
|
INSP-Supply line flush | 1/21/2015 | 1/21/2015 | 1/21/2015 | P | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Sprinkler Rough-in | 12/11/2014 | 12/11/2014 | 12/11/2014 | P | PART |
Forrest France
|
|
|
Overhead tenting inspection completed satisfactory.
|
INSP-Sprinkler Rough-in | 12/1/2014 | 12/2/2014 | 12/2/2014 | A | PART |
Troy Cobbley
|
|
|
Rough-in passed. FDC and riser not installed yet.
|
INSP-Sprinkler Rough-in | 9/5/2014 | 9/5/2014 | 9/5/2014 | P | PASS |
Troy Cobbley
|
|
|
Underground supply piping is ok to cover.
|
Permit Ready to Issue | | | 8/6/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Issue and Print Permit | | | 8/6/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Inspection Record Card- Fire | 8/6/2014 | | 8/6/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Plan assigned to (Tim) | 7/30/2014 | | 7/30/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 7/30/2014 | | 7/30/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 7/30/2014 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/30/2014 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 7/26/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 26 2014 1:04PM
|