INSP-Final Inspection | 2/26/2015 | 2/26/2015 | 2/26/2015 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 2/24/2015 | 2/25/2015 | 2/25/2015 | A | CANC |
Troy Cobbley
|
|
|
Overbooked
|
INSP-Sprinkler Rough-in/Hydro | 1/22/2015 | 1/26/2015 | 1/26/2015 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed.
|
INSP-Supply line flush | 1/21/2015 | 1/22/2015 | 1/22/2015 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Sprinkler Rough-in | 12/2/2014 | 12/2/2014 | 12/2/2014 | P | PASS |
Troy Cobbley
|
|
|
Tenting repaired. Piping can be covered.
|
INSP-Sprinkler Rough-in | 12/1/2014 | 12/2/2014 | 12/2/2014 | A | FAIL |
Troy Cobbley
|
|
|
Tenting is inadequate. Piping can not be covered until tenting inspection has passed
|
INSP-Sprinkler Rough-in | 11/19/2014 | 11/20/2014 | 11/20/2014 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can not be covered until a tenting inspection has passed.
|
INSP-Sprinkler Rough-in | 9/5/2014 | 9/5/2014 | 9/5/2014 | P | PASS |
Troy Cobbley
|
|
|
Underground supply line cover ok
|
Permit Ready to Issue | | | 8/6/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Issue and Print Permit | | | 8/6/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Inspection Record Card- Fire | 8/6/2014 | | 8/6/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Plan assigned to (Tim) | 7/30/2014 | | 7/30/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 7/30/2014 | | 7/30/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 7/30/2014 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/30/2014 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 7/26/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 26 2014 1:08PM
|