INSP-Final Inspection | 9/17/2014 | 9/18/2014 | 9/18/2014 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 9/17/2014 | 9/18/2014 | 9/17/2014 | A | CANC |
Troy Cobbley
|
|
|
Chris to attend Phone #: ###-#### >> Inspection requested via web by Connie Danes Inspection cancelled from web by: Connie Danes
|
INSP-Sprinkler Rough-in | 9/16/2014 | 9/17/2014 | 9/17/2014 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping is ok to cover
|
Permit Ready to Issue | | | 8/19/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 8/19/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 8/19/2014 | | 8/19/2014 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 8/15/2014 | | 8/15/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/15/2014 | | DONE |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 8/7/2014 | | 8/7/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/7/2014 | | 8/7/2014 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 8/7/2014 | | FAIL |
Tim Frost
|
|
|
|
Early Start | | | 8/7/2014 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 7/31/2014 | | DONE |
|
|
|