Permit Information
Permit NumberFIR14-00569
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 6165 W EMERALD ST
Project NameSt. Al's Joint (JCOE) Building
Customer NumberUDG ONLY
ePlanReviewYes
Description
Install a new 6" x 304 C-900 UG piping, fittings and thrust blocks to service the new fire sprinkler system.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/25/20153/25/20153/25/2015PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Sprinkler Rough-in2/5/20152/6/20152/6/2015PPASS
DetailsTroy Cobbley
See the city approved plans for locations marked where piping can be covered.
INSP-Sprinkler Rough-in2/3/20152/4/20152/4/2015ACANC
DetailsTroy Cobbley
Wrong permit number called in.
INSP-Sprinkler Rough-in2/3/20152/4/20152/3/2015PCANC
DetailsTroy Cobbley
This is an Visual OH/RTC inspection. Mike S is your contact. Please call 1/2 hour prior to inspection. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
INSP-Sprinkler Rough-in/Hydro12/4/201412/5/201412/5/2014PPART
DetailsTroy Cobbley
The sprinkler rough-in has generally passed and the piping above hardlids can be covered. There are several problems 1. The exterior walls have wood sheating with only insulation and a vapor barrier and no upright sprinkler protection, 2. Earth quake bracing is not attached to the building structure but is attached to the wall studs, 3. Ball drip is mounted outside of the building, 4. Approved plans show all branchlines coming from the sides of the main but as installed all branchlines come off of the main piping on riser nipples which will effect the hydraulic calculations. Plans need to be resubmitted.
INSP-Sprinkler Rough-in/Hydro10/1/201410/1/201410/1/2014PPASS
DetailsTroy Cobbley
The underground hydro test passed
INSP-Sprinkler Rough-in/Hydro9/19/20149/22/20149/22/2014PCANC
DetailsTroy Cobbley
Cancel per Mike due to no access to riser because of concrete and United Water has not turned on the site water yet.
INSP-Sprinkler Rough-in8/21/20148/22/20148/22/2014PPASS
DetailsTroy Cobbley
Underground supply piping is ok for cover.
Plan assigned to (Tim)8/8/2014 8/8/2014 DONE
DetailsTim Frost
Sprinkler Plan Check8/8/2014 8/8/2014 PASS
DetailsTim Frost
Please, see attached comments.
1st review completed  8/8/2014 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  8/8/2014 DONE
DetailsTim Frost
Permit Ready to Issue  8/8/2014 DONE
DetailsCandy A. Nichols
Issue and Print Permit  8/8/2014 DONE
DetailsCandy A. Nichols
Inspection Record Card- Fire8/8/2014 8/8/2014 DONE
DetailsCandy A. Nichols
Application received  8/7/2014 DONE
Application submitted via PDS Online on Aug 7 2014 1:15PM