Miscellaneous action | | | 10/2/2014 | | DONE |
|
|
|
As built drawings received.
|
INSP-Final Inspection | 9/26/2014 | 9/26/2014 | 9/26/2014 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Alarm Testing | 9/19/2014 | 9/22/2014 | 9/22/2014 | A | DONE |
Troy Cobbley
|
|
|
FACP interconnection with the new canopy dry system passed. Included low air, water flow and tamper switches.
|
Permit Ready to Issue | | | 8/20/2014 | | DONE |
Tisha Gallop
|
|
|
|
Issue and Print Permit | | | 8/20/2014 | | DONE |
Tisha Gallop
|
|
|
|
Inspection Record Card- Fire | 8/20/2014 | | 8/20/2014 | | DONE |
Tisha Gallop
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 8/18/2014 | | DONE |
|
|
|
Plans approved with review comments. Projectdox updated.
|
Plan assigned to (Lee) | 8/15/2014 | | 8/15/2014 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 8/15/2014 | | PASS |
|
|
|
|
Alarm Plan Check | 8/15/2014 | | 8/15/2014 | | PASS |
Lee G Meredith
|
|
|
|
Application received | | | 8/13/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 13 2014 5:00PM
|