DOC - Permit Finaled | | | 1/10/2019 | | DONE |
|
|
|
Informed by Chrissten Gregory that the hydro test was completed and passed with no other work required.
|
INSP-Sprinkler Rough-in/Hydro | 9/26/2014 | 9/29/2014 | 9/29/2014 | A | PASS |
Troy Cobbley
|
|
|
Underground hydro test passed
|
INSP-Sprinkler Rough-in | 9/23/2014 | 9/24/2014 | 9/24/2014 | A | PASS |
Troy Cobbley
|
|
|
Last part of underground ok to cover
|
INSP-Sprinkler Rough-in | 9/11/2014 | 9/11/2014 | 9/11/2014 | P | PASS |
Troy Cobbley
|
|
|
Approved cover for partial underground. See the city approved plans for locations.
|
Permit Ready to Issue | | | 9/2/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 9/2/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/2/2014 | | 9/2/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Tim) | 8/27/2014 | | 8/27/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 8/27/2014 | | 8/27/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 8/27/2014 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/27/2014 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 8/21/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 21 2014 2:38PM
|