Permit Information
Permit NumberFIR14-00612
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 1124 S ROOSEVELT ST
Project NameRed Rock Christian Church
Customer Number 
ePlanReviewYes
Description
Install one wet pipe fire protection system through out the heated areas, install a one dry pipe Fire Protection system through out the unheated attic portion of the existing Red Rock Church.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/1/201412/2/201412/2/2014APASS
DetailsForrest France
Fire sprinkler permit work passed final walkthrough and inspection. Forward flow, trip testing and sprinkler monitoring completed. Permit finaled.
INSP-Sprinkler Rough-in/Hydro11/25/201411/26/201412/1/2014APART
DetailsForrest France
Concluded satisfactory 24 hr. pneumatic testing of the new dry system within allowable limits per NFPA 13. Finished 11/26 AM.
INSP-Sprinkler Rough-in11/24/201411/25/201411/25/2014APART
DetailsForrest France
Begin 24hr air test at 10:30AM @ 46psig
INSP-Sprinkler Rough-in/Hydro11/24/201411/24/201411/24/2014PPART
DetailsForrest France
Overhead hydrostatic test of the new dry system completed satisfactory.
INSP-Sprinkler Rough-in/Hydro11/21/201411/24/201411/24/2014APART
DetailsForrest France
Completed overhead hydrostatic test of the new wet system piping and inspection for cover at grid ceilings in the new multipurpose room and adjacent corridor north end.
INSP-Sprinkler Rough-in11/17/201411/17/201411/17/2014PPART
DetailsForrest France
Rough-in as noted on plans to date approved for cover.
INSP-Sprinkler Rough-in11/4/201411/5/201411/5/2014APART
DetailsForrest France
Completed inspection for the new dry system mains and branchlines including the exterior soffits and attic spaces. Need to provide coverage below the elevated catwalk or meet exceptions allowed per NFPA. Remainder of coverage okayed, DP are not yet installed.
INSP-Sprinkler Rough-in10/14/201410/15/201410/15/2014APART
DetailsForrest France
Rough-in inspections completed for the following areas; multipurpose gym, main only at the riser room thru to the north addition hallway, new multipurpose room 202, conference room 119, food bank 114. Verified corrections at the sanctuary mezzanine. Refer to plans for dated annotations.
INSP-Sprinkler Rough-in/Hydro9/30/201410/1/201410/1/2014APART
DetailsForrest France
Overhead rough-in for portions of the wet system as marked and dated on plans approved for cover. Need to add upright protection at two areas in the sanctuary mechanical room as noted. Discussed sheetrock lid repair where removed for baffle install.
INSP-Sprinkler Rough-in9/30/201410/1/201410/1/2014APART
DetailsForrest France
Intended for an UG fire supply line hydrostatic test
Sprinkler Plan Check9/22/2014 9/22/2014 PASS
DetailsTim Frost
Please, see attached comments.
PLANS/APPL TAKEN TO FRONT DESK  9/22/2014 DONE
DetailsTim Frost
Permit Ready to Issue  9/22/2014 DONE
Issue and Print Permit  9/22/2014 DONE
Inspection Record Card- Fire9/22/2014 9/22/2014 DONE
DetailsChristina Prado
Miscellaneous action  9/19/2014 DONE
Some of the comments were not addressed tin the cross section view on drawing FP1. I cannot finish review unitl I get some difinitive answers. I am trying not to deny the review again. The review will be on hold until I hear from the designer.
Miscellaneous action  9/12/2014 PEND
Asked Chris to do another calculation in a different area. I am concerned the riser nipple sizes are not adequated. The project is on hold until I hear from Chris.
Sprinkler Plan Check9/2/2014 9/2/2014 FAIL
DetailsTim Frost
1st review completed  9/2/2014 FAIL
DetailsTim Frost
Miscellaneous action  9/2/2014 DONE
DetailsTim Frost
Emailed contractor in regards to failed review.
Plan assigned to (Tim)8/29/2014 8/29/2014 DONE
DetailsTim Frost
Application received  8/22/2014 DONE
Application submitted via PDS Online on Aug 22 2014 6:43AM