INSP-Final Inspection | 12/1/2014 | 12/2/2014 | 12/2/2014 | A | PASS |
Forrest France
|
|
|
Fire sprinkler permit work passed final walkthrough and inspection. Forward flow, trip testing and sprinkler monitoring completed. Permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 11/25/2014 | 11/26/2014 | 12/1/2014 | A | PART |
Forrest France
|
|
|
Concluded satisfactory 24 hr. pneumatic testing of the new dry system within allowable limits per NFPA 13. Finished 11/26 AM.
|
INSP-Sprinkler Rough-in | 11/24/2014 | 11/25/2014 | 11/25/2014 | A | PART |
Forrest France
|
|
|
Begin 24hr air test at 10:30AM @ 46psig
|
INSP-Sprinkler Rough-in/Hydro | 11/24/2014 | 11/24/2014 | 11/24/2014 | P | PART |
Forrest France
|
|
|
Overhead hydrostatic test of the new dry system completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 11/21/2014 | 11/24/2014 | 11/24/2014 | A | PART |
Forrest France
|
|
|
Completed overhead hydrostatic test of the new wet system piping and inspection for cover at grid ceilings in the new multipurpose room and adjacent corridor north end.
|
INSP-Sprinkler Rough-in | 11/17/2014 | 11/17/2014 | 11/17/2014 | P | PART |
Forrest France
|
|
|
Rough-in as noted on plans to date approved for cover.
|
INSP-Sprinkler Rough-in | 11/4/2014 | 11/5/2014 | 11/5/2014 | A | PART |
Forrest France
|
|
|
Completed inspection for the new dry system mains and branchlines including the exterior soffits and attic spaces. Need to provide coverage below the elevated catwalk or meet exceptions allowed per NFPA. Remainder of coverage okayed, DP are not yet installed.
|
INSP-Sprinkler Rough-in | 10/14/2014 | 10/15/2014 | 10/15/2014 | A | PART |
Forrest France
|
|
|
Rough-in inspections completed for the following areas; multipurpose gym, main only at the riser room thru to the north addition hallway, new multipurpose room 202, conference room 119, food bank 114. Verified corrections at the sanctuary mezzanine. Refer to plans for dated annotations.
|
INSP-Sprinkler Rough-in/Hydro | 9/30/2014 | 10/1/2014 | 10/1/2014 | A | PART |
Forrest France
|
|
|
Overhead rough-in for portions of the wet system as marked and dated on plans approved for cover. Need to add upright protection at two areas in the sanctuary mechanical room as noted. Discussed sheetrock lid repair where removed for baffle install.
|
INSP-Sprinkler Rough-in | 9/30/2014 | 10/1/2014 | 10/1/2014 | A | PART |
Forrest France
|
|
|
Intended for an UG fire supply line hydrostatic test
|
Sprinkler Plan Check | 9/22/2014 | | 9/22/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/22/2014 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 9/22/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 9/22/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/22/2014 | | 9/22/2014 | | DONE |
Christina Prado
|
|
|
|
Miscellaneous action | | | 9/19/2014 | | DONE |
|
|
|
Some of the comments were not addressed tin the cross section view on drawing FP1. I cannot finish review unitl I get some difinitive answers. I am trying not to deny the review again. The review will be on hold until I hear from the designer.
|
Miscellaneous action | | | 9/12/2014 | | PEND |
|
|
|
Asked Chris to do another calculation in a different area. I am concerned the riser nipple sizes are not adequated. The project is on hold until I hear from Chris.
|
Sprinkler Plan Check | 9/2/2014 | | 9/2/2014 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 9/2/2014 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 9/2/2014 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Plan assigned to (Tim) | 8/29/2014 | | 8/29/2014 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 8/22/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 22 2014 6:43AM
|