INSP-Final Inspection | 12/10/2014 | 12/11/2014 | 12/12/2014 | A | PART |
Craig D. Hanson
|
|
|
Exit signs need added in 3 locations. back middle of salesa floor, and each side of front of sales floor.
|
INSP-Sprinkler Rough-in | 11/4/2014 | 11/4/2014 | 11/4/2014 | P | PASS |
Troy Cobbley
|
|
|
Dry sidwalls located under the front canopy passed inspection.
|
INSP-Sprinkler Rough-in | 10/31/2014 | 10/31/2014 | 10/31/2014 | P | PASS |
Troy Cobbley
|
|
|
Remaining office area ceilings can be installed to cover piping.
|
INSP-Sprinkler Rough-in/Hydro | 10/16/2014 | 10/17/2014 | 10/17/2014 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro and riser rough-in passed.
|
INSP-Sprinkler Rough-in | 10/14/2014 | 10/14/2014 | 10/14/2014 | P | PART |
Troy Cobbley
|
|
|
Rough-in passed for exposed pipe. Still need cover inspections for areas where ceilings are not complete yet. Also riser has not been built/inspected yet.
|
INSP-Sprinkler Rough-in | 9/24/2014 | 9/24/2014 | 9/24/2014 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations where piping can be covered by the new hardlids.
|
Miscellaneous action | | | 9/23/2014 | | DONE |
|
|
|
Spoke with Clark - GC, in regards to the antifreeze system. Appartenly there is a wall separating Dicks Sporting Goods roof from the adjoing roof for snow loading purposes. I told him I was ok with filling it full of insulation, provided there is no ignition sources and it is fire stopped into 160^3 foot sections. I told him I would need a letter in writing for the file.
____________________
Spoke with Ron Steinquist 9/22/2014 and changed the barriers to every 1000^3 instead of 160^3
|
Sprinkler Plan Check | 9/5/2014 | | 9/5/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/5/2014 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 9/5/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 9/5/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/5/2014 | | 9/5/2014 | | DONE |
Kristal Soland
|
|
|
|
Sprinkler Plan Check | 8/28/2014 | | 8/28/2014 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 8/28/2014 | | FAIL |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 8/27/2014 | | 8/27/2014 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 8/22/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 22 2014 11:51AM
|