INSP-Final Inspection | 4/24/2015 | 4/24/2015 | 4/24/2015 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 3/23/2015 | 3/23/2015 | 3/23/2015 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed
|
INSP-Supply line flush | 3/18/2015 | 3/19/2015 | 3/19/2015 | P | PART |
Forrest France
|
|
|
UG fire supply line flush completed satisfactory.
|
INSP-Sprinkler Rough-in | 3/13/2015 | 3/16/2015 | 3/16/2015 | A | PASS |
Troy Cobbley
|
|
|
Tenting passed. Piping is ok to cover
|
INSP-Sprinkler Rough-in | 3/12/2015 | 3/12/2015 | 3/12/2015 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping matches plans. Piping can not be covered untill a tenting inspection has been performed.
|
INSP-Sprinkler Rough-in | 3/11/2015 | 3/11/2015 | 3/12/2015 | P | CANC |
Troy Cobbley
|
|
|
Overbooked. Rescheduled for 3/12/15
|
INSP-Sprinkler Rough-in | 3/10/2015 | 3/10/2015 | 3/10/2015 | P | FAIL |
Troy Cobbley
|
|
|
Pipe sizing as installed does not match the approved plans. Also no tenting of the sprinkler piping has been performed. No piping to be covered.
|
INSP-Sprinkler Rough-in | 2/18/2015 | 2/18/2015 | 2/18/2015 | P | PASS |
Troy Cobbley
|
|
|
Underground is ok to cover.
|
INSP-Sprinkler Rough-in | 2/17/2015 | 2/17/2015 | 2/17/2015 | P | CANC |
Troy Cobbley
|
|
|
Underground not ready for inspection
|
Permit Ready to Issue | | | 9/9/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 9/9/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/9/2014 | | 9/9/2014 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 9/4/2014 | | 9/4/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 9/4/2014 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/4/2014 | | DONE |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 9/3/2014 | | 9/3/2014 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 8/23/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 23 2014 10:40AM
|