INSP-Final Inspection | 6/9/2015 | 6/10/2015 | 6/10/2015 | A | PASS |
Katie Marron
|
|
|
Scope of Work complete. Verified electric alarm bell has been relocated to front. Permit finaled.
|
INSP-Final Inspection | 5/15/2015 | 5/15/2015 | 5/15/2015 | P | FAIL |
Troy Cobbley
|
|
|
Final passed and underground flush passed. Will be ok to final when the electric alarm bell has been relocated to the front of the house.
|
INSP-Sprinkler Rough-in/Hydro | 12/18/2014 | 12/18/2014 | 12/18/2014 | A | PART |
Forrest France
|
|
|
Rough-in and tenting inspections passed. Verified heating to be provided at the shop room adjacent to the garage. Plan mod okayed.
|
INSP-Sprinkler Rough-in | 12/17/2014 | 12/17/2014 | 12/18/2014 | P | DEFR |
Forrest France
|
|
|
|
Sprinkler Plan Check | 12/17/2014 | | 12/17/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/17/2014 | | DONE |
Tim Frost
|
|
|
|
CHANGE STATUS TO (ISS) | | | 12/17/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Sprinkler Plan Check | 12/10/2014 | | 12/10/2014 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 12/10/2014 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
INSP-Sprinkler Rough-in/Hydro | 11/6/2014 | 11/7/2014 | 11/7/2014 | A | PART |
Forrest France
|
|
|
UG fire supply line okayed for bury.
|
Permit Ready to Issue | | | 10/3/2014 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 10/3/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/3/2014 | | 10/3/2014 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 9/30/2014 | | 9/30/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/30/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 9/19/2014 | | 9/19/2014 | | FAIL |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 9/4/2014 | | 9/4/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 9/4/2014 | | 9/4/2014 | | FAIL |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 9/4/2014 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 9/4/2014 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 8/25/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 25 2014 8:38AM
|