Permit NumberFIR14-00628
StatusFinaled
Name SHILO AUTOMATIC SPRINKLER CO
Site Address 1105 S LA POINTE ST
Project NameSherwood Apartments
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of providing a dry system for a parking garage. The 6” underground supplies a 6” backflow preventer to a 6” header. There is a 4” dry pipe riser and a 6” feed main supplied from the 6” header. The 6” feed main supplies the standpipes and floor level control valves above.

The 6” main located on level one above the ceiling will be heat traced, insulated and monitored.

The underground piping is under permit FIR14-00478

West Sherwood Apartments - Building 1 - To construct a 41,670 square foot, three story, wood framed apartment building. This building contains 57 living units. This building is being constructed on a three-hour fire-resistive concrete podium above a one-story concrete parking garage building. This apartment building is being divided into three buildings by two firewalls.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Miscellaneous action  9/2/2015 DONE
Heat tracing is no longer required per project HVAC contractor. See letter located in ProjectDOX document folder and revised drawing FP-3
INSP-Final Inspection7/26/20157/27/20157/27/2015APASS
DetailsJim Page
Previously noted items corrected, Dry pendant escutcheons on order, will be installed when received, fire sprinkler inspection passed/complete
INSP-Final Inspection7/23/20157/24/20157/24/2015APART
DetailsJim Page
Trip test of the dry pipe valve, including the new accelerator - tested OK within 45 seconds. Escutcheons missing on multiple heads in parking area, need to have air maintenance installed on air line supply to dry system, compressor provided regulator not approved for air maintenance.
INSP-Final Inspection7/20/20157/20/20157/20/2015PFAIL
DetailsThomas Walsh
Trip test of dry pipe valve protecting perking garage. Trip test resulted in 90 seconds to delivery of water to IT. Contractro agreed to install an accelerator to get within 60 seconds timeframe. All other tests, including low-air, tampers, ext. bell, etc., tested OK
INSP-Sprinkler Rough-in/Hydro7/16/20157/16/20157/16/2015PPASS
DetailsThomas Walsh
Hydrotest (200 psi @ 2hrs.) of dry pipe system protecting parking garage level.
PASSED
Sprinkler Plan Check9/4/2014 9/4/2014 PASS
DetailsTim Frost
Please, see attached comments.
1st review completed  9/4/2014 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  9/4/2014 DONE
DetailsTim Frost
Permit Ready to Issue  9/4/2014 DONE
Issue and Print Permit  9/4/2014 DONE
Inspection Record Card- Fire9/4/2014 9/4/2014 DONE
DetailsKristal Soland
Plan assigned to (Tim)9/3/2014 9/3/2014 DONE
DetailsTim Frost
Application received  8/25/2014 DONE
Application submitted via PDS Online on Aug 25 2014 4:29PM