INSP-Final Inspection | 9/29/2014 | 9/29/2014 | 9/29/2014 | P | PASS |
Forrest France
|
|
|
Fire alarm permit work approved for final.
|
INSP-Alarm Testing | 9/25/2014 | 9/26/2014 | 9/26/2014 | P | PASS |
Forrest France
|
|
|
Fire alarm testing passed after corrections made while on site.
|
Permit Ready to Issue | | | 9/2/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 9/2/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/2/2014 | | 9/2/2014 | | DONE |
Christina Prado
|
|
|
|
1st review completed | | | 8/28/2014 | | FAIL |
|
|
|
Plans returned on pre screen review. Riser and floor plans don't match, visual notification inadequate in one room, load calculations are not correct. I notified the designer of the corrections required via email.
|
Plan resubmittals received | | | 8/28/2014 | | DONE |
|
|
|
|
Alarm Plan Check | 8/28/2014 | | 8/28/2014 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 8/28/2014 | | DONE |
|
|
|
Plans approved with review comments. Projectdox updated.
|
Plan assigned to (Lee) | 8/27/2014 | | 8/27/2014 | | DONE |
Lee G Meredith
|
|
|
|
Miscellaneous action | | | 8/27/2014 | | DONE |
|
|
|
Due to projectdox issues, Uploadcomplete task completed by Alex DeYoung at applicant's request
|
Application received | | | 8/26/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 26 2014 1:47PM
|