INSP-Final Inspection | 2/19/2015 | 2/20/2015 | 2/20/2015 | P | PASS |
Forrest France
|
|
|
Verified approved plans. Points map to be posted today as agreed. Fire alarm permit finaled.
|
INSP-Final Inspection | 2/12/2015 | 2/17/2015 | 2/17/2015 | A | PART |
Forrest France
|
|
|
Completed functional testing of the common area horns and strobes per the written scope of work at floor levels basement thru 3rd. Missing approved plans on site for verification of design and install- final pending.
|
INSP-Final Inspection | 11/19/2014 | 11/20/2014 | 11/20/2014 | P | CANC |
Troy Cobbley
|
|
|
To be canceled per Nathan Price and my discussion due to sync issues between the new and existing horns.
|
Miscellaneous action | | | 9/9/2014 | | DONE |
|
|
|
Corrections made but scale is still off by 1/2. I emailed Rita a screen capture of the scale to show the problem. Sh resubmitted again with the corrections complete.
|
Alarm Plan Check | 9/9/2014 | | 9/9/2014 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 9/9/2014 | | DONE |
|
|
|
Plans approved with review comments. Projectdox updated.
|
Permit Ready to Issue | | | 9/9/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Issue and Print Permit | | | 9/9/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Inspection Record Card- Fire | 9/9/2014 | | 9/9/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Plan assigned to (Lee) | 9/8/2014 | | 9/8/2014 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 9/8/2014 | | FAIL |
|
|
|
Scale on floor plans incorrect.
|
Miscellaneous action | | | 9/8/2014 | | DONE |
|
|
|
Emailed applicant review comments.
|
Miscellaneous action | | | 9/8/2014 | | DONE |
|
|
|
Drawings resubmitted but scale is still wrong. I emailed Rita Doty to let her know that the scale graph is still off by 1/2.
|
Application received | | | 9/4/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 4 2014 4:58PM
|