INSP-Final Inspection | 1/6/2015 | 1/7/2015 | 1/7/2015 | A | PASS |
Forrest France
|
|
|
Scope of permit work completed. Fire sprinkler permit finaled.
|
INSP-Final Inspection | 9/19/2014 | 9/19/2014 | 9/19/2014 | P | NR |
Forrest France
|
|
|
Project not in condition for final at this time.
|
INSP-Sprinkler Rough-in | 9/19/2014 | 9/19/2014 | 9/19/2014 | P | PART |
Forrest France
|
|
|
Verified removal of the cooler and dry pendent. New ssp installed but missing grid and ceiling at this time. No access to complete inspection of work at the basement.
|
Sprinkler Plan Check | 9/15/2014 | | 9/15/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/15/2014 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 9/15/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 9/15/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 9/15/2014 | | 9/15/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Tim) | 9/11/2014 | | 9/11/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 9/11/2014 | | 9/11/2014 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 9/11/2014 | | FAIL |
Tim Frost
|
|
|
|
Application received | | | 9/8/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 8 2014 2:33PM
|