INSP-Final Inspection | 3/6/2015 | 3/9/2015 | 3/10/2015 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. Alarms are latching
|
INSP-Final Inspection | 3/5/2015 | 3/6/2015 | 3/6/2015 | A | FAIL |
Troy Cobbley
|
|
|
General alarm signals to be set up as latching, need map a facp mounted
|
INSP-Final Inspection | 12/11/2014 | 12/12/2014 | 12/12/2014 | P | FAIL |
Troy Cobbley
|
|
|
Was only able to verify netcon, PIV and wet system flow switch. Duct smoke detectors were not connected to thermostats so that they could be turned on. Need to test dry system devices and hoods in the Chinese Restraunt.
|
INSP-Final Inspection | 11/12/2014 | 11/13/2014 | 11/13/2014 | P | CANC |
Troy Cobbley
|
|
|
Cancel per John Phone #: ###-####
|
Permit Ready to Issue | | | 10/8/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/8/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/8/2014 | | 10/8/2014 | | DONE |
Christina Prado
|
|
|
|
1st review completed | | | 9/26/2014 | | PASS |
|
|
|
|
Alarm Plan Check | 9/26/2014 | | 9/26/2014 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 9/26/2014 | | DONE |
|
|
|
Plans approved with review comments. Projectdox updated.
|
Telephone call | | | 9/24/2014 | | DONE |
|
|
|
John Lopez call to inform me that there are existing seperation walls. He will resubmit the drawings indicating where the walls are located and include their ratings.
|
Plan assigned to (Lee) | 9/22/2014 | | 9/22/2014 | | DONE |
Lee G Meredith
|
|
|
|
Telephone call | | | 9/22/2014 | | DONE |
|
|
|
I informed John Lopez that if putting in new fire alarm panels in this and the adjacent building (FIR14-00691) the occuplant load will require that full notification be installed in each building. He is going to contact the owner to see how to proceed.
|
Application received | | | 9/19/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 19 2014 9:56AM
|