INSP-Final Inspection | 5/17/2018 | 5/22/2018 | 5/22/2018 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 2/20/2018 | 2/23/2018 | 2/23/2018 | A | FAIL |
Troy Cobbley
|
|
|
The outside electric alarm bell can be silenced from the FACP which is not allowed. All other items appear ok.
Natalie Phone #: ###-####
|
(F) Reprint permit | | | 10/17/2017 | | DONE |
|
|
|
|
INSP-Final Inspection | 9/5/2017 | 9/6/2017 | 9/6/2017 | A | FAIL |
Troy Cobbley
|
|
|
Not ready for final yet. Today we tested the additional strobe in the short corridor that was added. Hvac unit would not shut down upon activation of the smoke detector.
John Lopez Phone #: ###-####
|
INSP-Final Inspection | 9/1/2017 | 9/1/2017 | 9/1/2017 | P | CANC |
Troy Cobbley
|
|
|
John Phone #: ###-####
|
INSP-Final Inspection | 8/18/2017 | 8/22/2017 | 8/22/2017 | P | FAIL |
Troy Cobbley
|
|
|
Need as-builts addressing the device locations and candella changes, hvac unit needs wired for shutdown, need map, need notification in short corridor, need flow switch tested.. All other devices tested
|
Miscellaneous action | | | 5/3/2017 | | DONE |
|
|
|
John Lopez responded via email that he was on site eariler this week and found that phase 2 is in progress. Once completed, he will schedule a final test.
|
Miscellaneous action | | | 5/2/2017 | | DONE |
|
|
|
Emailed John to request a progress update on completeion of the project. Informed him the Fire Marshal would like the job completed or canceled.
|
Miscellaneous action | | | 1/17/2017 | | DONE |
|
|
|
John Lopez emailed to ask if resubmittal was required to maintain the issued status of this aging permit. I informed him that would not require a resubmittal as long as significant changes have not been made.
|
INSP-Conference | 12/6/2016 | 12/6/2016 | 12/6/2016 | P | DONE |
Scott Arellano
|
|
|
Onsite visit to check on progress and meet with owner. Construction work remains in progress. Advised owners representatives to have fire protection contractors call in for testing and inspection of completed systems for partial completion.
|
INSP-Conference | 12/2/2016 | 12/2/2016 | 12/2/2016 | A | DONE |
Troy Cobbley
|
|
|
I contacted John via email and he is going to follow up with the church and get back to me.
|
INSP-Final Inspection | 9/8/2015 | 9/10/2015 | 9/10/2015 | P | CANC |
Troy Cobbley
|
|
|
Cancel per John Phone #: ###-####
|
INSP-Final Inspection | 8/19/2015 | 8/20/2015 | 8/20/2015 | A | FAIL |
Troy Cobbley
|
|
|
See the city approved plans for building area where I tested today. Some corrections have been noted. Not all construction is complete or fire alarm installed.
|
INSP-Final Inspection | 8/13/2015 | 8/18/2015 | 8/18/2015 | A | FAIL |
Katie Marron
|
|
|
No City approved drawings or submittals were on site. Inspection to be rescheduled.
|
INSP-Final Inspection | 7/7/2015 | 7/9/2015 | 7/9/2015 | P | CANC |
Troy Cobbley
|
|
|
John Phone #: ###-####
|
Permit Ready to Issue | | | 10/8/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/8/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/8/2014 | | 10/8/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Lee) | 9/26/2014 | | 9/26/2014 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 9/26/2014 | | PASS |
|
|
|
|
Alarm Plan Check | 9/26/2014 | | 9/26/2014 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 9/26/2014 | | DONE |
|
|
|
plans approved with review comments. Projectdox updated.
|
Application received | | | 9/25/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 25 2014 9:47AM
|