INSP-Final Inspection | 12/3/2014 | 12/3/2014 | 12/3/2014 | P | PASS |
Forrest France
|
|
|
Verified C/N items, as-built plans accepted. Points map and record of completion documents to be provided as agreed.
|
INSP-Alarm Testing | 12/1/2014 | 12/2/2014 | 12/2/2014 | A | PART |
Forrest France
|
|
|
Functional testing and inspection of the new fire alarm system completed. Items needed prior to final include as-built drawings reflecting field modifications to show four added strobes, deleted kitchen hood monitor, revised cd settings at the multi-purpose rooms and west corridor, riser points added for dry system pressure switches. Need to add notification at the kitchen area restroom. Post signage at the door to the FACP room.
|
Permit Ready to Issue | | | 10/30/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/30/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/30/2014 | | 10/30/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Lee) | 10/29/2014 | | 10/29/2014 | | DONE |
Lee G Meredith
|
|
|
|
Miscellaneous action | | | 10/29/2014 | | DONE |
|
|
|
Plans uploade to projectdox on 10-24-14
|
1st review completed | | | 10/29/2014 | | PASS |
|
|
|
|
Alarm Plan Check | 10/29/2014 | | 10/29/2014 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 10/29/2014 | | DONE |
|
|
|
Plans approved with review comments and conditions. Projectdox updated.
|
Telephone call | | | 10/1/2014 | | DONE |
|
|
|
Ken Webster call to inform me that although he has submitted his application and documents, He does not have a returned set from the engineer of record. Once he has received this, he will submit it and complete the upload process to start the work flow. He did not have an estimate on when this would be done so there may be an extended delay before plan review can be completed.
|
Telephone call | | | 10/1/2014 | | DONE |
|
|
|
Ken Webster call to indicate that duct smoke detectors are required, in his opinion but they are not shown on the drawings. The engineer of record feels that they are not requires and stated this in an RFI response to Ken.
|
Application received | | | 9/30/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Sep 30 2014 10:16AM
|