Information based on query as of Friday, June 28, 2024.
Permit Information
Permit NumberFIR14-00729
StatusFinaled
Name SIMPLEX GRINNELL
Site Address 5301 E WARM SPRINGS AVE
Project NameTerraces of Boise Wings CDE
Customer Number 
ePlanReviewYes
Description
Wings C, D & E consists of complete notification system, add transponder 1 and using transpondere 2 from F wing. Both are being networked with the main FACP at H wing. Associated with building permit BLD13-00182.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection11/10/201511/10/201511/10/2015PPASS
DetailsJim Page
Final fire alarm passed/complete per activities entered by Tom Walsh on 29OCT2015.
INSP-Final Inspection10/29/201510/29/201510/29/2015PPASS
DetailsThomas Walsh
Final inspection/test of fire alarm system, including all fire sprinkler interface devices tested OK. Final inspection for these wings has passed.
INSP-Alarm Testing10/7/201510/7/201510/7/2015PPART
DetailsThomas Walsh
Test and inspection of fire alarm system for Wing E, including elevator lobby and resident storage areas of the parking garage. Tested manual pulls, SDs, SFDs notification and in-room SDs, sprinkler waterflows, tampers, trip test of dry-pipe system, elevator recall functions, shunt trip, etc. for all of Wing E. Some devices near stair F1 had to be rewired to wing E, as they were located within the TCO area.
All fire alarm system devices tested OK for this wing. Since TCO of wing E is approved by this office, the fire alarm and fire sprinkler systems shall remain in service at all times.
CHANGE STATUS TO (ISS)  10/7/2015 DONE
DetailsChristina Prado
Per request from Scott Arellano, status changed to ISS
INSP-Final Inspection6/12/20156/15/20156/15/2015APART
DetailsThomas Walsh
Final inspection of Bldg. D and commons area for phase 1 TCO area. All HVAC units SD units tested OK. All other devices tested OK with previous inspections.
Only outstanding item for this phase, is to clean up FACP room so that the cover on the SD above the panel can be uncovered. Currently, this SD needs to be covered as the room ventilation system is not operable, and the exterior door is propped open to provide ventilation. This should be completed within the next day or so.
Other than that, the fire alarm system for Bldg's A, B, C and D, including the parking garage under all, is currently on line and fully operational.
INSP-Final Inspection6/12/20156/12/20156/12/2015APART
DetailsThomas Walsh
Final inspection of fire alarm systems for Wings C & D, including elevator recall functions and SFDs - PASSED
INSP-Alarm Testing6/8/20156/8/20156/8/2015PPART
DetailsThomas Walsh
Inspection/ test of fire alarm system for the permit coverage area, including manual pulls, smoke detection, waterflows, tamper supervisories, and audibility/visual device testing. All addresses appeared to be accurate.
NOTE: No FSDs or elevator functions tested this visit.
INSP-Conference5/21/20155/22/20155/22/2015ADONE
DetailsThomas Walsh
Met with Brian Anderson (Simplex Grinnel) to discuss expectations for testing of phase 1 and TCO of this area while work on phase 2 is ongoing. I told Brian that it is our expectation that the phase 1 portion of the system be completely 100% pretested, with all coorections made, prior to calling us for our inspection/test. He said that he will communicate this to the GC.
Permit Ready to Issue  11/25/2014 DONE
Issue and Print Permit  11/25/2014 DONE
Inspection Record Card- Fire11/25/2014 11/25/2014 DONE
DetailsChristina Prado
Alarm Plan Check11/24/2014 11/24/2014 PASS
DetailsLee G Meredith
PLANS TAKEN FRONT DESK ALARM  11/24/2014 DONE
Resubmittal approved with review comments and requirements. Projectdox updated.
Plan resubmittals received  11/20/2014 DONE
1st review completed  10/15/2014 FAIL
see 1st review comments.
Miscellaneous action  10/15/2014 DONE
Emailed review comments to applicant.
CHANGE STATUS TO (REV)  10/13/2014 DONE
DetailsChristina Prado
Plan assigned to (Lee)10/9/2014 10/9/2014 DONE
DetailsScott Arellano
Application received  10/3/2014 DONE
Application submitted via PDS Online on Oct 3 2014 2:55PM