INSP-Final Inspection | 6/1/2015 | 6/2/2015 | 6/3/2015 | P | PASS |
Thomas Walsh
|
|
|
Completion of 24 hour air test of dry pipe valve (PASSED) and trip test of the DP valve, which flowed full pressure at the inspectors test valve in 80 seconds after DPV activation. Fire alarm interface not tested this visit.
|
INSP-Sprinkler Rough-in | 6/1/2015 | 6/1/2015 | 6/1/2015 | P | PART |
Thomas Walsh
|
|
|
24 hour air test - 40 psi at 1330 hrs.
|
INSP-Sprinkler Rough-in/Hydro | 6/1/2015 | 6/2/2015 | 6/1/2015 | P | CANC |
Thomas Walsh
|
|
|
trip test Please call Leroy 30 min prior ###-#### Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
INSP-Sprinkler Rough-in/Hydro | 5/21/2015 | 5/21/2015 | 5/21/2015 | P | PASS |
Thomas Walsh
|
|
|
Bldg. D dry pipe system hydrotest - 200psi @ 2 hours - Passed
|
INSP-Sprinkler Rough-in/Hydro | 4/14/2015 | 4/14/2015 | 4/14/2015 | P | PART |
Katie Marron
|
|
|
Area D Porte Cochere dry system ok to cover per plans. Entry vestibule was not complete at this time.
|
INSP-Sprinkler Rough-in | 4/13/2015 | 4/14/2015 | 4/14/2015 | A | CANC |
Katie Marron
|
|
|
Rough in Porte Cochere - Dry Please contact Leroy 30 min prior ###-#### Phone #: ###-#### >> Inspection requested via web by Jacci Hunt Inspection cancelled from web by: Jacci Hunt
|
INSP-Sprinkler Rough-in | 1/20/2015 | 1/21/2015 | 1/21/2015 | A | PART |
Forrest France
|
|
|
Work completed to date on area D dry system inspected to plan modification drawings. Install at the porte cochere is unfinished at this time.
|
Sprinkler Plan Check | 1/20/2015 | | 1/20/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/20/2015 | | DONE |
Tim Frost
|
|
|
|
Inspection Record Card- Fire | 1/20/2015 | | 1/20/2015 | | DONE |
Kristal Soland
|
|
|
|
CHANGE STATUS TO (ISS) | | | 1/20/2015 | | DONE |
|
|
|
|
Miscellaneous action | | | 1/14/2015 | | DONE |
|
|
|
Had another meeting today. Discussed the situation with Plan Mod drawings. It was decided they would mark up the drawing in red of actual as built installation. I will preliminary review the markup to look for any obvious errors. I would ok the drawings and inform Forest. At the end of the job, proper as built drawings will be created. This is to expedite the continous field changes to the approved drawings.
In addition, I was informed the dormers were not drawn correctly. The actual dormers are much smaller. The bottom right corner has also apparently shrunk from what was shown on the drawings. Phoenix Fire Protection indicated to me the areas are properly protected. I have marked the drawings asking Forest to please verify actual field conditions.
This was the fifth meeting discussing communication challengs between Phoneix design deparment and myself.
|
Sprinkler Plan Check | 1/14/2015 | | 1/14/2015 | | FAIL |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 1/9/2015 | | 1/9/2015 | | FAIL |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 12/20/2014 | | 12/20/2014 | | FAIL |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 12/20/2014 | | 12/20/2014 | | DONE |
Tim Frost
|
|
|
|
INSP-Sprinkler Rough-in | 12/8/2014 | 12/9/2014 | 12/9/2014 | P | FAIL |
Forrest France
|
|
|
Numerous field modifications to main, and branchline routing, deleted and added heads including branchlines at several locations, major elevation changes not indicated, changes to types of heads installed at specific areas- Need to provide a resubmittal prior to rough-in and cover inspection approval. Some areas incomplete, missing sprinklers, two eves are not covered.
|
INSP-Sprinkler Rough-in | 11/26/2014 | 12/1/2014 | 12/9/2014 | P | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in | 11/19/2014 | 11/20/2014 | 11/20/2014 | A | FAIL |
Troy Cobbley
|
|
|
This was for Bldg D dry system. Heads overspaced, additional fittings and heads blocked by obstructions. Plans need to be resubmitted that match the actual layout. No piping to be covered. Only inspected area at remote area. Did not look at hangers, bracing or restraints.
|
INSP-Sprinkler Rough-in | 11/18/2014 | 11/18/2014 | 11/19/2014 | P | NR |
Forrest France
|
|
|
Missing stamped approved plans on site.
|
Permit Ready to Issue | | | 11/10/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/10/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/10/2014 | | 11/10/2014 | | DONE |
Christina Prado
|
|
|
|
Sprinkler Plan Check | 11/7/2014 | | 11/7/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/7/2014 | | DONE |
Tim Frost
|
|
|
|
Plan assigned to (Tim) | 10/24/2014 | | 10/24/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 10/24/2014 | | 10/24/2014 | | FAIL |
Tim Frost
|
|
|
Correctr previouse review items that were not addressed
|
Plan assigned to (Tim) | 10/13/2014 | | 10/13/2014 | | DONE |
Tim Frost
|
|
|
|
Intake Approval | | | 10/13/2014 | | PASS |
|
|
|
|
Sprinkler Plan Check | 10/13/2014 | | 10/13/2014 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 10/13/2014 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 10/13/2014 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Application received | | | 10/10/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 10 2014 9:21AM
|
INSP-Sprinkler Rough-in | 11/24/2014 | 11/25/2014 | | A | |
Forrest France
|
|
|
RTC for Dry System, Bldg D 1st floor, please call Scott 30 minutes prior at ###-#### Phone #: ###-#### >> Inspection requested via web by Jacci Hunt
|