INSP-Final Inspection | 1/29/2015 | 1/30/2015 | 1/30/2015 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 1/28/2015 | 1/29/2015 | 1/29/2015 | A | FAIL |
Troy Cobbley
|
|
|
Outside alarm bell did not ring upon activation of the dry pipe system.
|
INSP-Sprinkler Rough-in/Hydro | 1/20/2015 | 1/21/2015 | 1/21/2015 | P | PASS |
Troy Cobbley
|
|
|
24 hr air test passed
|
INSP-Sprinkler Rough-in/Hydro | 1/20/2015 | 1/20/2015 | 1/20/2015 | P | PART |
Troy Cobbley
|
|
|
Rick-24 hr air test started at 10:00am with 40 psi on the guage
|
INSP-Sprinkler Rough-in/Hydro | 1/15/2015 | 1/16/2015 | 1/16/2015 | A | PASS |
Troy Cobbley
|
|
|
Overhead 200lb hydro for both the wet and dry systems passed.
|
INSP-Sprinkler Rough-in | 1/14/2015 | 1/15/2015 | 1/15/2015 | A | PASS |
Troy Cobbley
|
|
|
Piping in office area can be covered. 6" main installed and passed. Heads under doors installed and passed
|
INSP-Sprinkler Rough-in | 12/29/2014 | 12/30/2014 | 12/30/2014 | A | PASS |
Troy Cobbley
|
|
|
6" main needs to be installed/inspected and the tie-in's to the existing system. Outside canopy is ok to cover. Need sprinkler coverage installed under doors.
|
Sprinkler Plan Check | 12/22/2014 | | 12/22/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/22/2014 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 12/22/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 12/22/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Inspection Record Card- Fire | 12/22/2014 | | 12/22/2014 | | DONE |
Candy A. Nichols
|
|
|
|
INSP-Sprinkler Rough-in | 12/19/2014 | 12/19/2014 | 12/19/2014 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler piping above the restrooms is ok to cover.
|
INSP-Sprinkler Rough-in | 10/29/2014 | 10/29/2014 | 10/29/2014 | P | PASS |
Troy Cobbley
|
|
|
The 5'-0" stub out is ok to bury.
|
(F) Reprint permit | | | 10/16/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Inspection Record Card- Fire | 10/16/2014 | | 10/16/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Miscellaneous action | | | 10/15/2014 | | DONE |
|
|
|
Requested additional information via email
Do you have the existing hydraulic calculations?
What was the original flow test information?
Did the existing riser have a backflow preventer?
Can you email a set of the existing drawings and calculations?
Is there an additional lead in?
How many square foot is in this system including the existing and new?
I am concerned if the existing system will still function properly hydraulically.
In addition, if this is all one system, it may well be over 52k sqft.
|
Sprinkler Plan Check | 10/15/2014 | | 10/15/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 10/15/2014 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/15/2014 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 10/15/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Issue and Print Permit | | | 10/15/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Inspection Record Card- Fire | 10/15/2014 | | 10/15/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Plan assigned to (Tim) | 10/14/2014 | | 10/14/2014 | | DONE |
Tim Frost
|
|
|
|
Intake Approval | | | 10/14/2014 | | PASS |
|
|
|
|
Miscellaneous action | | | 10/14/2014 | | DONE |
|
|
|
Email for more information.
Hello Nathan,
I have a few general questions is regards to this project. Please, respond back in email.
1. What exactly is being done in the Paint Department Expansion?
2. I notice there is a large opening into the existing building from the Paint Department Expansion. Does this opening have a fire door?
3. What exactly is being done on the adjacent/existing side of the opening?
4. Is there a spray paint booth in the current project area?
5. Is there any flammable liquid spraying in the project area? If so where exactly?
|
Miscellaneous action | | | 10/14/2014 | | DONE |
|
|
|
Response from email
Tim,
Please see below answers in red. Let me know if you have any other questions.
Thanks,
Nathan Stenquist
Project Design
Treasure Valley Fire Protection
I have a few general questions is regards to this project. Please, respond back in email.
1. What exactly is being done in the Paint Department Expansion? The dealership will use this are to prep vehicles for paint (i.e. wash and stage).
2. I notice there is a large opening into the existing building from the Paint Department Expansion. Does this opening have a fire door? There will be no fire door.
3. What exactly is being done on the adjacent/existing side of the opening? Currently the existing area is being used for the same type of prep and the only painting is done in the paint booth in the SE corner of the building.
4. Is there a spray paint booth in the current project area? There will be no paint booth in the new project area.
5. Is there any flammable liquid spraying in the project area? If so where exactly? There will be no flammable liquid spraying in the new project area. The only spraying will be in the existing paint booth that was previously properly protected and not in our current scope.
Cordially,
Tim Frost, S.E.T.
Fire Sprinkler Plans Examiner
Fire Code Plans Examiner
|
Application received | | | 10/13/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 13 2014 10:39AM
|