INSP-Final Inspection | 8/19/2015 | 8/20/2015 | 8/20/2015 | P | PASS |
Jim Page
|
|
|
Final fire sprinkler inspection passed/complete
|
INSP-Sprinkler Rough-in/Hydro | 6/9/2015 | 6/10/2015 | 6/10/2015 | A | PASS |
Troy Cobbley
|
|
|
Overhead rough-in/tenting inspection complete. Piping can be covered. I spoke to Anderson Construction about making sure the tenting was not modified after I inspect. They were going to meet with the tenting contractor to verify
|
INSP-Sprinkler Rough-in/Hydro | 6/1/2015 | 6/2/2015 | 6/2/2015 | P | PASS |
Jim Page
|
|
|
Fire sprinkler overhead hydrostatic test passed/complete.
|
INSP-Supply line flush | 5/27/2015 | 5/28/2015 | 5/28/2015 | A | PASS |
Troy Cobbley
|
|
|
Supply line flush passed
|
INSP-Sprinkler Rough-in | 4/23/2015 | 4/23/2015 | 4/23/2015 | P | PASS |
Troy Cobbley
|
|
|
Underground supply piping is ok to cover
|
Permit Ready to Issue | | | 11/5/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Issue and Print Permit | | | 11/5/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Inspection Record Card- Fire | 11/5/2014 | | 11/5/2014 | | DONE |
Candy A. Nichols
|
|
|
|
Plan assigned to (Tim) | 10/27/2014 | | 10/27/2014 | | DONE |
Tim Frost
|
|
|
|
Intake Approval | | | 10/27/2014 | | PASS |
|
|
|
|
Sprinkler Plan Check | 10/27/2014 | | 10/27/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 10/27/2014 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/27/2014 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 10/15/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 15 2014 6:58PM
|