INSP-Final Inspection | 7/27/2015 | 7/27/2015 | 7/27/2015 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 7/24/2015 | 7/27/2015 | 7/27/2015 | P | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### >> Inspection requested via web by Sam Ball Inspection cancelled from web by: Sam Ball
|
INSP-Final Inspection | 7/23/2015 | 7/24/2015 | 7/24/2015 | A | CANC |
Troy Cobbley
|
|
|
To be rescheduled for monday
|
INSP-Sprinkler Rough-in/Hydro | 6/1/2015 | 6/2/2015 | 6/2/2015 | P | PASS |
Jim Page
|
|
|
Fire sprinkler overhead hydrostatic test passed/complete.
|
INSP-Supply line flush | 5/27/2015 | 5/28/2015 | 5/27/2015 | A | PASS |
Troy Cobbley
|
|
|
Supply line flush passed
|
INSP-Sprinkler Rough-in/Hydro | 5/26/2015 | 5/27/2015 | 5/27/2015 | P | PASS |
Troy Cobbley
|
|
|
Rough-in and tenting inspeciton passed. Piping can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 4/14/2015 | 4/15/2015 | 4/15/2015 | A | PASS |
Troy Cobbley
|
|
|
Underground ok to cover
|
Permit Ready to Issue | | | 11/5/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/5/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/5/2014 | | 11/5/2014 | | DONE |
Kristal Soland
|
|
|
|
Plan assigned to (Tim) | 10/20/2014 | | 10/20/2014 | | DONE |
Tim Frost
|
|
|
|
Intake Approval | | | 10/20/2014 | | PASS |
|
|
|
|
Sprinkler Plan Check | 10/20/2014 | | 10/20/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 10/20/2014 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/20/2014 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 10/15/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 15 2014 7:15PM
|