INSP-Final Inspection | 6/10/2015 | 6/11/2015 | 6/11/2015 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 6/4/2015 | 6/5/2015 | 6/5/2015 | A | PASS |
Jim Page
|
|
|
Overhead fire sprinkler hydrostatic test passed/complete
|
INSP-Sprinkler Rough-in/Hydro | 6/3/2015 | 6/3/2015 | 6/3/2015 | A | CANC |
Jim Page
|
|
|
Cancelled from point of cotact at job site, Absolute Fire Phone # ###-####, building not ready for hydrostatic test at this time.
|
INSP-Supply line flush | 5/27/2015 | 5/28/2015 | 5/28/2015 | A | PASS |
Troy Cobbley
|
|
|
Supply line flush passed
|
INSP-Sprinkler Rough-in | 4/30/2015 | 5/1/2015 | 5/1/2015 | A | PASS |
Troy Cobbley
|
|
|
Tenting and rough-in passed. Piping can be covered.
|
INSP-Sprinkler Rough-in | 4/15/2015 | 4/15/2015 | 4/16/2015 | P | PASS |
Troy Cobbley
|
|
|
Underground supply is ok to cover
|
Permit Ready to Issue | | | 11/5/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/5/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/5/2014 | | 11/5/2014 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Tim) | 10/27/2014 | | 10/27/2014 | | DONE |
Tim Frost
|
|
|
|
Intake Approval | | | 10/27/2014 | | PASS |
|
|
|
|
Sprinkler Plan Check | 10/27/2014 | | 10/27/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 10/27/2014 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/27/2014 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 10/15/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 15 2014 7:45PM
|