INSP-Final Inspection | 8/31/2015 | 9/1/2015 | 9/1/2015 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in | 7/14/2015 | 7/15/2015 | 7/15/2015 | A | PASS |
Troy Cobbley
|
|
|
Sprinkler rough-in and tenting passed. Piping can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 6/3/2015 | 6/3/2015 | 6/3/2015 | A | PASS |
Jim Page
|
|
|
Fire sprinkler overhead hydrostatic test passed/complete.
|
INSP-Supply line flush | 5/27/2015 | 5/28/2015 | 5/28/2015 | A | PASS |
Troy Cobbley
|
|
|
Supply line flush passed
|
INSP-Sprinkler Rough-in | 3/31/2015 | 3/31/2015 | 3/31/2015 | P | PASS |
Troy Cobbley
|
|
|
Underground piping is ok to cover
|
Fees Due Hold | 11/5/2014 | | 11/5/2014 | | DONE |
|
|
|
|
Fees Due Hold | 11/4/2014 | | 11/4/2014 | | DONE |
|
|
|
|
Intake Approval | | | 11/3/2014 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 11/3/2014 | | 11/3/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 11/3/2014 | | 11/3/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 11/3/2014 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/3/2014 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 11/3/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/3/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/3/2014 | | 11/3/2014 | | DONE |
Kristal Soland
|
|
|
|
Application received | | | 10/15/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 15 2014 8:25PM
|