INSP-Final Inspection | 12/1/2014 | 12/1/2014 | 12/1/2014 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in | 10/27/2014 | 10/27/2014 | 10/27/2014 | P | PART |
Troy Cobbley
|
|
|
Sprinkler rough-in passed but I found an area at the north wall that is lacking sprinkler coverage. I will verify coverage at the final inspection. Piping is ok to cover.
|
Permit Ready to Issue | | | 10/24/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/24/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/24/2014 | | 10/24/2014 | | DONE |
Kristal Soland
|
|
|
|
Plan assigned to (Tim) | 10/23/2014 | | 10/23/2014 | | DONE |
Tim Frost
|
|
|
|
Intake Approval | | | 10/23/2014 | | PASS |
|
|
|
|
Sprinkler Plan Check | 10/23/2014 | | 10/23/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 10/23/2014 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/23/2014 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 10/22/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 22 2014 9:36AM
|