INSP-Final Inspection | 12/15/2014 | 12/15/2014 | 12/15/2014 | P | PASS |
Forrest France
|
|
|
Verified noted coverage adjustments. Fire sprinkler permit finaled.
|
INSP-Final Inspection | 12/11/2014 | 12/11/2014 | 12/11/2014 | P | PART |
Forrest France
|
|
|
Original scope of work per plan completed- final pending coverage adjustment at one office per field inspection.
|
INSP-Sprinkler Rough-in | 11/7/2014 | 11/10/2014 | 11/10/2014 | A | PASS |
Troy Cobbley
|
|
|
Rough-in passed. Piping can be covered.
|
Permit Ready to Issue | | | 10/24/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 10/24/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 10/24/2014 | | 10/24/2014 | | DONE |
Kristal Soland
|
|
|
|
Plan assigned to (Tim) | 10/23/2014 | | 10/23/2014 | | DONE |
Tim Frost
|
|
|
|
Intake Approval | | | 10/23/2014 | | PASS |
|
|
|
|
Sprinkler Plan Check | 10/23/2014 | | 10/23/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 10/23/2014 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/23/2014 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 10/22/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 22 2014 11:52AM
|