INSP-Final Inspection | 5/22/2015 | 5/22/2015 | 5/22/2015 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in | 2/18/2015 | 2/19/2015 | 2/19/2015 | P | PASS |
Troy Cobbley
|
|
|
UG/Flush passed. I noted the possible need for branch line restraints and plan modifications if the four additional elbows on the branchlines have not been included in the hydraulic calculations
|
INSP-Sprinkler Rough-in | 11/20/2014 | 11/21/2014 | 11/21/2014 | P | PASS |
Troy Cobbley
|
|
|
Underground ok to cover. Installation routing does not match plans. Actual installation shall match on the overhead piping drawings.
|
Permit Ready to Issue | | | 11/3/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/3/2014 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 11/3/2014 | | 11/3/2014 | | DONE |
Kristal Soland
|
|
|
|
Intake Approval | | | 10/29/2014 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 10/29/2014 | | 10/29/2014 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 10/29/2014 | | 10/29/2014 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 10/29/2014 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/29/2014 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 10/27/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Oct 27 2014 9:54AM
|