Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR14-00799
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 5369 W IRVING ST
Project NameSIMPLOT PLANT SCIENCES BLDG. A
Customer Number 
ePlanReviewYes
Description
The fire sprinkler scope of work consists of adding, plugging and relocating sprinklers to accommodate new wall and ceiling configuration.

Simplot Plant Science - Construct research lab space in an existing storage portion of existing research lab facility. Scope of work to include new exterior exit off second floor, new elevator, foundation and site work for additional elevator lobby of 653 sq. ft. and 3,720 sq. ft. on second floor and remodel of 4,879 sq. ft. on first floor.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/29/20157/29/20157/29/2015PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection7/23/20157/24/20157/24/2015AFAIL
DetailsTroy Cobbley
No access to room because of flooring and many of the sprinkler heads still had protection on them by painters. No inspection completed.
INSP-Conference7/1/20157/1/20157/1/2015PDONE
DetailsTroy Cobbley
Rick and I met to discuss sprinkler obstructions. I deferred him to plan review.
INSP-Sprinkler Rough-in6/26/20156/26/20156/26/2015PPART
DetailsJim Page
Contractor re-configured head placement in growth chambers,east side of building first floor, instead of 4 pendants contractor changed to two sidewalls, coverage works with application. Contractor will notate on as-build drawings the change in head lauout.
INSP-Sprinkler Rough-in5/20/20155/21/20155/21/2015APASS
DetailsTroy Cobbley
Second floor rough-in passed. As-builts will be required for pipe routing changes and head additions.
INSP-Sprinkler Rough-in/Hydro5/18/20155/18/20155/18/2015PPASS
DetailsTroy Cobbley
1st floor overhead hydro passed
INSP-Sprinkler Rough-in5/14/20155/15/20155/15/2015APART
DetailsTroy Cobbley
First floor rough-in passed. Need to address combustible concealed space at entrance. Hydro test failed. Second floor lobby area rough-in passed. Head in bottom of elevator shaft passed.
INSP-Sprinkler Rough-in/Hydro5/11/20155/11/20155/11/2015PPART
DetailsKatie Marron
Four hard lid areas on second floor ok to cover.
Permit Ready to Issue  11/12/2014 DONE
Issue and Print Permit  11/12/2014 DONE
Inspection Record Card- Fire11/12/2014 11/12/2014 DONE
DetailsChristina Prado
Sprinkler Plan Check11/7/2014 11/7/2014 PASS
DetailsTim Frost
Please, see attached comments.
1st review completed  11/7/2014 PASS
DetailsTim Frost
PLANS/APPL TAKEN TO FRONT DESK  11/7/2014 DONE
DetailsTim Frost
Plan assigned to (Tim)11/3/2014 11/3/2014 DONE
DetailsTim Frost
Intake Approval  11/3/2014 FAIL
Failed Prescreen, missine elevation on Owner's Certificate.
Application received  10/29/2014 DONE
Application submitted via PDS Online on Oct 29 2014 11:28AM