Case Summary | | | 6/3/2016 | | DONE |
|
|
|
|
INSP-Final Inspection | 4/30/2015 | 5/1/2015 | 5/1/2015 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 4/19/2015 | 4/20/2015 | 4/20/2015 | A | FAIL |
Troy Cobbley
|
|
|
Need to provide correct height for the exterior strob on roof and all emergency lights prior to a final sign off.. All other items tested ok.
|
Miscellaneous action | | | 4/15/2015 | | DONE |
|
|
|
Received as built drawings and uploaded them to projectdox.
|
Telephone call | | | 2/5/2015 | | DONE |
|
|
|
Bill Benko called to discuss central station monitoring requirements. He said that the fire alarm contractor wants to provide a new dialer for this site but Bill doesn't want multiple monitoring services. I suggested that he contact his current provider to see if the existing dialer can provide seperate building signals. He sent the specifications over for review. It was generic but did cover the obligation through code reference to meet IFC and NFPA 72requirements.
|
Permit Ready to Issue | | | 1/30/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 1/30/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/30/2015 | | 1/30/2015 | | DONE |
Christina Prado
|
|
|
|
Plan resubmittals received | | | 1/27/2015 | | DONE |
|
|
|
Resubmittal based on review comments received.
|
Alarm Plan Check | 1/27/2015 | | 1/27/2015 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 1/27/2015 | | DONE |
|
|
|
Plan resubmittal review appreoved with comments. Projectdox updated.
|
Miscellaneous action | | | 1/15/2015 | | DONE |
|
|
|
Emailed failed review comments to applicant.
|
Plan assigned to (Lee) | 1/14/2015 | | 1/14/2015 | | DONE |
Lee G Meredith
|
|
|
Rick Groom provided revised floor plans with ceiling heights and beam details.
|
Alarm Plan Check | 1/14/2015 | | 1/14/2015 | | FAIL |
Lee G Meredith
|
|
|
See 1st plan review comments.
|
Miscellaneous action | | | 11/19/2014 | | DONE |
|
|
|
Rick Groom emailed ceiling heights that vary from 12 feet to 27 feet. This may have an effect on the heat detector placement. Rick is also looking at exposed ceiling beams that may also impact spacing. Once he has the information, he will determine if a resubmittal is needed.
|
Plan assigned to (Lee) | 11/12/2014 | | 11/12/2014 | | DONE |
Lee G Meredith
|
|
|
|
Application received | | | 11/10/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Nov 10 2014 2:59PM
|
1st review completed | | | 1/15/2014 | | FAIL |
|
|
|
See 1st review comments.
|