Case Summary | | | 6/3/2016 | | DONE |
|
|
|
|
INSP-Final Inspection | 7/1/2015 | 7/1/2015 | 7/1/2015 | A | PASS |
Jim Page
|
|
|
Fire alarm inspection passed/complete
|
Fees Due Hold | 12/14/2014 | | 1/12/2015 | | DONE |
Christina Prado
|
|
|
|
1st review completed | | | 11/21/2014 | | PASS |
|
|
|
|
Alarm Plan Check | 11/21/2014 | | 11/21/2014 | | PASS |
Lee G Meredith
|
|
|
|
Plan assigned to (Lee) | 11/21/2014 | | 11/21/2014 | | DONE |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 11/21/2014 | | DONE |
|
|
|
Plans approved on site. Permit is ready for processing.
|
Permit Ready to Issue | | | 11/21/2014 | | DONE |
|
|
|
|
Issue and Print Permit | | | 11/21/2014 | | DONE |
|
|
|
|
Application received | | | 11/13/2014 | | DONE |
Mary Froemke
|
|
|
This permit was created on the web by Paul Marcolina
|
Application received | | | 11/13/2014 | | DONE |
|
|
|
This permit was created on the web by Paul Marcolina
|