INSP-Final Inspection | 4/20/2015 | 4/21/2015 | 4/21/2015 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 4/17/2015 | 4/20/2015 | 4/20/2015 | A | PART |
Troy Cobbley
|
|
|
Forward flush passed. Could not test flows and tampers due to fire alarm issues.
|
INSP-Sprinkler Rough-in/Hydro | 4/14/2015 | 4/14/2015 | 4/14/2015 | P | PASS |
Troy Cobbley
|
|
|
24hr air test on dry system passed
|
INSP-Sprinkler Rough-in/Hydro | 4/13/2015 | 4/13/2015 | 4/13/2015 | P | PART |
Troy Cobbley
|
|
|
24 hour air test started on dry system at 2pm with 43 psi on the guage.
|
INSP-Sprinkler Rough-in/Hydro | 4/10/2015 | 4/13/2015 | 4/13/2015 | A | PASS |
Troy Cobbley
|
|
|
Overhead 200lb hydro for the wet and dry systems passed. Overhead rough-in for the wet and dry systems passed.
|
INSP-Sprinkler Rough-in | 3/31/2015 | 3/31/2015 | 3/31/2015 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed for the office area, first and second floors, piping can be covered.
|
Sprinkler Plan Check | 3/4/2015 | | 3/4/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/4/2015 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 3/4/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Issue and Print Permit | | | 3/4/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Inspection Record Card- Fire | 3/4/2015 | | 3/4/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Sprinkler Plan Check | 3/3/2015 | | 3/3/2015 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 3/3/2015 | | FAIL |
Tim Frost
|
|
|
|
Intake Approval | | | 12/30/2014 | | FAIL |
|
|
|
|
Plan assigned to (Tim) | 12/30/2014 | | 12/30/2014 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 12/22/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 22 2014 7:14AM
|