INSP-Final Inspection | 8/20/2015 | 8/21/2015 | 8/21/2015 | A | PASS |
Jim Page
|
|
|
Final fire alarm inspection passed/complete
|
CHANGE STATUS TO (ISS) | | | 8/19/2015 | | DONE |
|
|
|
|
Alarm Plan Check | 8/18/2015 | | 8/18/2015 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 8/18/2015 | | DONE |
|
|
|
Plan modification approved.
|
Permit Ready to Issue | | | 8/18/2015 | | DONE |
|
|
|
please do not re issue
|
Plan resubmittals received | | | 8/17/2015 | | DONE |
|
|
|
Plan Modification submitted.
|
INSP-Final Inspection | 8/12/2015 | 8/12/2015 | 8/12/2015 | P | FAIL |
Troy Cobbley
|
|
|
Was only able to test the tamper for fire pump #1 suction valve today due to foam dump. Overhead doors and duct smoke detector not ready
|
INSP-Alarm Testing | 8/10/2015 | 8/11/2015 | 8/11/2015 | A | DONE |
Troy Cobbley
|
|
|
Todays testing included all tamper switches except Fire Pump #1 intake (needs replaced) and all flow and pressure switches. The hose valve tampers/riser are labeled incorrectly. Also tested the fire pump interconnection to the FACP. Risers and fire pumps need labeling to match the FACP display. Need signal reports. Need plans resubmitted due to extensive changes which include using a 4009 NAC panel for releasing and a wireless dialer instead of phone lines and door mags that need releasing upon flow of water.
|
Permit Ready to Issue | | | 2/26/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/26/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/26/2015 | | 2/26/2015 | | DONE |
Brittany Hill
|
|
|
|
Plan resubmittals received | | | 2/25/2015 | | DONE |
|
|
|
|
Alarm Plan Check | 2/25/2015 | | 2/25/2015 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 2/25/2015 | | DONE |
|
|
|
Plans approved with review comments. Projectdox updated.
|
Alarm Plan Check | 2/23/2015 | | 2/23/2015 | | FAIL |
Lee G Meredith
|
|
|
See 2nd review comments.
|
Miscellaneous action | | | 2/23/2015 | | DONE |
|
|
|
Emailed 2nd review comments to Dante Frassa.
|
Plan resubmittals received | | | 2/18/2015 | | DONE |
|
|
|
|
1st review completed | | | 12/29/2014 | | FAIL |
|
|
|
See review comments for all outstanding items with this review.
|
Plan assigned to (Lee) | 12/24/2014 | | 12/24/2014 | | DONE |
Lee G Meredith
|
|
|
|
Application received | | | 12/22/2014 | | DONE |
|
|
|
Application submitted via PDS Online on Dec 22 2014 3:39PM
|