INSP-Final Inspection | 7/14/2015 | 7/15/2015 | 7/15/2015 | P | PASS |
Jim Page
|
|
|
Previously noted items corrected, document cabinet with associated documents at the fire panel, sign posted on door leading to fire panel, alarm inspection passed/complete.
|
INSP-Final Inspection | 4/27/2015 | 4/28/2015 | 4/28/2015 | P | PART |
Katie Marron
|
|
|
Functional testing of new Alarm panel and radio transmitter complete. Verified NETCON, duct SD shut down of HVAC, all tampers, flows, and power troubles accurately reported panel and central station. Need document box, signage on door to panel and map of initiating devices posted at FACP to complete.
|
INSP-Final Inspection | 3/20/2015 | 3/23/2015 | 3/23/2015 | P | FAIL |
Forrest France
|
|
|
HVAC units did not shut down upon activation of duct smoke detectors, need to verify necton rating on site per review note comments, noted duct SD are programed as an alarm signal.
|
CHANGE STATUS TO (ISS) | | | 2/17/2015 | | DONE |
|
|
|
|
Plan resubmittals received | | | 2/13/2015 | | DONE |
|
|
|
|
Alarm Plan Check | 2/13/2015 | | 2/13/2015 | | PASS |
Lee G Meredith
|
|
|
Plan Modification
|
PLANS TAKEN FRONT DESK ALARM | | | 2/13/2015 | | DONE |
|
|
|
Plan modification approved with review comments. Projectdox updated.
|
Telephone call | | | 2/12/2015 | | DONE |
|
|
|
John Lopez called to say that he will be submitting a plan modification. When they came on site to install the new communicator, they found the fire alarm panel was not functional. A new panel will be installed with compatible devices. John is aware that the new panel requires the system to be brought up to current code. John indicated all that is required is sprinkler monitoring.
|
Permit Ready to Issue | | | 1/13/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 1/13/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Inspection Record Card- Fire | 1/13/2015 | | 1/13/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Plan assigned to (Lee) | 1/12/2015 | | 1/12/2015 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 1/12/2015 | | PASS |
|
|
|
|
Alarm Plan Check | 1/12/2015 | | 1/12/2015 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 1/12/2015 | | DONE |
|
|
|
Quick permit approved with no review comments. Projectdox updated.
|
Application received | | | 1/8/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 8 2015 1:23PM
|