INSP-Final Inspection | 8/13/2015 | 8/14/2015 | 8/14/2015 | A | PASS |
Lee G Meredith
|
|
|
Previously noted items corrected, fire alarm inspection passed/complete
|
INSP-Final Inspection | 8/12/2015 | 8/13/2015 | 8/13/2015 | A | FAIL |
Troy Cobbley
|
|
|
We tested the elevator and it did recall the elevator but did not set off the new notification circuits. Tested some of the hvac units but could not get all of them to turn on. When notification circuits were activated there is sync issue. Testing stopped.
|
INSP-Final Inspection | 8/11/2015 | 8/12/2015 | 8/12/2015 | P | CANC |
Troy Cobbley
|
|
|
Overbooked. To be rescheduled
|
INSP-Final Inspection | 8/4/2015 | 8/5/2015 | 8/5/2015 | P | FAIL |
Troy Cobbley
|
|
|
See the city approved plans for modifications needed to the notification circuits. The only initiating devices tested today are the two elevator lobby detectors which functioned correctly.
|
Permit Ready to Issue | | | 1/20/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 1/20/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/20/2015 | | 1/20/2015 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Lee) | 1/16/2015 | | 1/16/2015 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 1/16/2015 | | PASS |
|
|
|
|
Alarm Plan Check | 1/16/2015 | | 1/16/2015 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 1/16/2015 | | DONE |
|
|
|
Plans approved with review notes and drawing notation. Projectdox updated.
|
Application received | | | 1/15/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 15 2015 4:32PM
|