Case Summary | | | 6/6/2016 | | DONE |
|
|
|
|
DOC - Permit Finaled | | | 6/25/2015 | | DONE |
|
|
|
Per LGM 5/15/15
|
INSP-Final Inspection | 4/30/2015 | 5/1/2015 | 5/1/2015 | A | PASS |
Lee G Meredith
|
|
|
Tested & approved by Troy Cobbley.
|
INSP-Final Inspection | 4/29/2015 | 4/30/2015 | 4/30/2015 | A | CANC |
Troy Cobbley
|
|
|
Not ready for testing. Waiting on AES under separate permit
|
Plan assigned to (Lee) | 1/23/2015 | | 1/23/2015 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 1/23/2015 | | PASS |
|
|
|
|
Alarm Plan Check | 1/23/2015 | | 1/23/2015 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 1/23/2015 | | DONE |
|
|
|
Plans approved with review comments. Projectdox updated.
|
Permit Ready to Issue | | | 1/23/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 1/23/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 1/23/2015 | | 1/23/2015 | | DONE |
Kristal Soland
|
|
|
|
Application received | | | 1/17/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 17 2015 11:23AM
|