INSP-Final Inspection | 5/11/2015 | 5/11/2015 | 5/11/2015 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
CHANGE STATUS TO (ISS) | | | 4/7/2015 | | DONE |
|
|
|
as per Troy Cobbley was finaled by mistake
|
INSP-Final Inspection | 4/2/2015 | 4/2/2015 | 4/2/2015 | P | PASS |
Troy Cobbley
|
|
|
Work is not yet complete at the south/east main exit (pendant head is overspaced)
|
INSP-Sprinkler Rough-in | 3/25/2015 | 3/26/2015 | 3/26/2015 | P | PASS |
Troy Cobbley
|
|
|
Piping ok to cover at the Bakery soffits
|
INSP-Sprinkler Rough-in | 2/25/2015 | 2/26/2015 | 2/26/2015 | A | PART |
Troy Cobbley
|
|
|
Piping is soffit is ok to cover, pendant heads will be required above small coolers as discussed
|
INSP-Sprinkler Rough-in | 2/25/2015 | 2/25/2015 | 2/25/2015 | P | CANC |
Troy Cobbley
|
|
|
Overbooked
|
INSP-Sprinkler Rough-in | 2/13/2015 | 2/17/2015 | 2/17/2015 | A | PASS |
Troy Cobbley
|
|
|
Partial ok to cover in Deli Area
|
Permit Ready to Issue | | | 2/13/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/13/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/13/2015 | | 2/13/2015 | | DONE |
Kristal Soland
|
|
|
|
Intake Approval | | | 1/28/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 1/28/2015 | | 1/28/2015 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 1/28/2015 | | 1/28/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 1/28/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 1/28/2015 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 1/23/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 23 2015 4:28PM
|