INSP-Final Inspection | 9/23/2015 | 9/24/2015 | 9/24/2015 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
Miscellaneous action | | | 9/23/2015 | | DONE |
|
|
|
As built drawings received
|
INSP-Alarm Testing | 6/15/2015 | 6/16/2015 | 6/16/2015 | A | DONE |
Troy Cobbley
|
|
|
Todays inspection was for the hvac shut down of the units on the second floor.
|
INSP-Alarm Testing | 6/9/2015 | 6/10/2015 | 6/10/2015 | P | DONE |
Troy Cobbley
|
|
|
Todays testing was for the hvac shut down on the first floor only. See the city approved plans for locations marked ok. Will need to test the detector over the security desk and the dampers/separation between floors when installed.
|
INSP-Sprinkler Rough-in | 6/1/2015 | 6/2/2015 | 6/2/2015 | A | PART |
Troy Cobbley
|
|
|
This inspection should have been scheduled as a final. A temporary occupancy is being given until the hvac shutdown, door mags and 3rd floor is complete.
|
INSP-Alarm Testing | 5/29/2015 | 6/1/2015 | 6/1/2015 | A | DONE |
Troy Cobbley
|
|
|
Water flow pressure switch has been corrected. Low air needs to be re-programmed. Need two door mag locks addressed as discussed. Tamper switches have been adjusted.
|
CHANGE STATUS TO (ISS) | | | 6/1/2015 | | DONE |
|
|
|
|
Telephone call | | | 5/29/2015 | | DONE |
|
|
|
Returned phone call to Cathy Miller of ECI regarding temporary occupancy requirements. Informed her that it may be considered if all fire, sprinkler and life safety issues need to be fully operational with the possible exception of new air shaft damper control. (not received or installed yet) Informed her that this needs to be complete within 30 days. She needs to get approval of this with the mechanical inspector as we don't have final say. She wanted to know if the mechanical control system could provide global shutdown of heat pumps. I informed her this could be done it the control system is UL listed for smoke control. Otherwise, each heat pump will require individual shutdown control by the fire alarm system. I also informed her that a formal request for temporary occupancies require a formal request by the building permit applicant.
|
Plan resubmittals received | | | 5/29/2015 | | DONE |
|
|
|
Dan Krisnek emailed to say that he had submitted plan modification drawings on 5-26. I informed him that I had not received notification. Workflow report showed that upload complete task had not been completed. I emailed instruction on how to complete this task. Notification was received about 10 minutes later.
|
Alarm Plan Check | 5/29/2015 | | 5/29/2015 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 5/29/2015 | | DONE |
|
|
|
Plan modification approved with review comments and specific reqirements. Projectdox updated.
|
INSP-Alarm Testing | 5/26/2015 | 5/27/2015 | 5/27/2015 | P | DONE |
Troy Cobbley
|
|
|
Todays inspection we verified the Faast detection system (problems with low air and water flow), and verified the devices in the Warehouse. I noted that door mags are being used for security and will need to be addressed with the appropriate Fire Code and NFPA requirements.
|
INSP-Final Inspection | 5/22/2015 | 5/27/2015 | 5/27/2015 | A | CANC |
Troy Cobbley
|
|
|
Duplicate inspection
|
INSP-Final Inspection | 5/22/2015 | 5/26/2015 | 5/26/2015 | A | FAIL |
Troy Cobbley
|
|
|
Fire alarm testing for the first and second floors is complete. Correction previously noted have been address. Need HVAC issues addressed on all floors and the third floor fire alarm work completed.
|
Telephone call | | | 5/26/2015 | | DONE |
|
|
|
Conference call with myself, Troy James, Mary Froemke and Cathy Miller of ECI and an owner's rep. The call was to confirm the allowance of plenum mounted area smoke detection within the listed spacing for return duct detection of numerous heat pumps that collectively exceed 2000 cfm. Case is to be opened to upload plan mod drawings.
|
INSP-Final Inspection | 5/22/2015 | 5/22/2015 | 5/22/2015 | P | FAIL |
Troy Cobbley
|
|
|
First floor corrections complete, second floor audio/visuals passed. Still need outside alarm bell repaired and heat detectors in elevator shafts tested. HVAC still needs to be addressed
|
INSP-Alarm Testing | 5/20/2015 | 5/21/2015 | 5/21/2015 | A | DONE |
Troy Cobbley
|
|
|
See the city approved plans for locations and devices tested which included the elevator recall. Elevator fire doors need to be adjusted/repaired, PIV needs adjusted and the outside alarm bell did not function.
|
INSP-Alarm Testing | 5/19/2015 | 5/20/2015 | 5/20/2015 | A | CANC |
Troy Cobbley
|
|
|
Ken and I agreed to reshedule for tomorrow morning at 7:00am
|
INSP-Alarm Testing | 5/18/2015 | 5/19/2015 | 5/19/2015 | A | DONE |
Troy Cobbley
|
|
|
Todays inspection verified the FACP and the NAC panel. Also verified tamper switches as marked on the city approved plans. Also verifed placement and function of the first floor NAC circuits/devices. I noted several overspaced strobes as marked on the plans. I spoke to the general contractor about duct smoke detectors (he is waiting on an RFI)
|
Permit Ready to Issue | | | 2/10/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/10/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/10/2015 | | 2/10/2015 | | DONE |
Kristal Soland
|
|
|
|
Alarm Plan Check | 2/9/2015 | | 2/9/2015 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 2/9/2015 | | DONE |
|
|
|
Plans approved with review comments. Projectdox updated.
|
Plan resubmittals received | | | 2/6/2015 | | DONE |
|
|
|
|
Plan assigned to (Lee) | 2/5/2015 | | 2/5/2015 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 2/5/2015 | | FAIL |
|
|
|
See 1st review comments.
|
Application received | | | 1/27/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Jan 27 2015 9:46AM
|