INSP-Final Inspection | 3/2/2015 | 3/3/2015 | 3/3/2015 | P | PASS |
Forrest France
|
|
|
Fire alarm testing completed satisfactory. As-builts recieved.
|
Miscellaneous action | | | 2/24/2015 | | DONE |
|
|
|
Ken Webster emailed to clarify his corridor design. He indicated that he used area spacing (NFPA 72 18.5.5.4) instead of corridor spacing (18.5.5.5) for strobes C-4-5 and C-4-7. The devices are shown at 15cd each. He says that C-4-5 is to be set at 30cd and C-4-7 is to be set at 75cd. He is to provide updated as built drawings to show the changes.
|
Permit Ready to Issue | | | 2/23/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/23/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/23/2015 | | 2/23/2015 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Lee) | 2/11/2015 | | 2/11/2015 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 2/11/2015 | | PASS |
|
|
|
|
Alarm Plan Check | 2/11/2015 | | 2/11/2015 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 2/11/2015 | | DONE |
|
|
|
Plans approved with review comments. Projectdox updated.
|
Application received | | | 2/7/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 7 2015 10:42AM
|