Case Summary | | | 6/6/2016 | | DONE |
|
|
|
|
INSP-Final Inspection | 3/6/2015 | 3/6/2015 | 3/6/2015 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Alarm Testing | 3/5/2015 | 3/6/2015 | 3/6/2015 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
Miscellaneous action | | | 3/4/2015 | | DONE |
|
|
|
Revised calculations missing. Contacted Damie and he emailed them.
|
Alarm Plan Check | 3/4/2015 | | 3/4/2015 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 3/4/2015 | | DONE |
|
|
|
Plan modification approved without additional review comments.
|
CHANGE STATUS TO (ISS) | | | 3/4/2015 | | DONE |
Candy A. Nichols
|
|
|
|
INSP-Final Inspection | 2/27/2015 | 3/3/2015 | 3/3/2015 | A | FAIL |
Troy Cobbley
|
|
|
Need all small documents (review notes, data sheets), need correct size of batteries, need wireless dialer approved, need additional stobe in alcove at old main entrance, need as-builts submitted to plan review showing relocation of the FACP and related Voice Evac. system. No testing performed today.
|
Plan resubmittals received | | | 3/3/2015 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 2/18/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 2/18/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 2/18/2015 | | 2/18/2015 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Lee) | 2/17/2015 | | 2/17/2015 | | DONE |
Lee G Meredith
|
|
|
|
Miscellaneous action | | | 2/17/2015 | | DONE |
|
|
|
Product data supplied for the pull station is not compatible with the fire alarm panel. I informed Damie and he emailed product data for one that will work.
|
1st review completed | | | 2/17/2015 | | PASS |
|
|
|
|
Alarm Plan Check | 2/17/2015 | | 2/17/2015 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 2/17/2015 | | DONE |
|
|
|
Plans approved with review comments and requirements noted on the floor plan. Projectdox updated.
|
Application received | | | 2/16/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 16 2015 3:14PM
|