INSP-Final Inspection | 4/16/2015 | 4/17/2015 | 4/17/2015 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 4/9/2015 | 4/9/2015 | 4/9/2015 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed
|
INSP-Sprinkler Rough-in/Hydro | 4/6/2015 | 4/7/2015 | 4/7/2015 | P | PASS |
Troy Cobbley
|
|
|
Sprinkler rough in pass, ok to cover pipe. Hydro test to be rescheduled
|
Permit Ready to Issue | | | 3/6/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/6/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Inspection Record Card- Fire | 3/6/2015 | | 3/6/2015 | | DONE |
Candy A. Nichols
|
|
|
|
Intake Approval | | | 3/3/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 3/3/2015 | | 3/3/2015 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 3/3/2015 | | 3/3/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 3/3/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/3/2015 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 2/20/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 20 2015 7:34AM
|