INSP-Final Inspection | 4/17/2015 | 4/17/2015 | 4/17/2015 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in | 3/24/2015 | 3/25/2015 | 3/25/2015 | A | PASS |
Troy Cobbley
|
|
|
Pharmacy piping is ok to re-cover.
|
INSP-Sprinkler Rough-in | 3/24/2015 | 3/24/2015 | 3/24/2015 | P | FAIL |
Troy Cobbley
|
|
|
Ceiling tile has been installed in the Pharmacy without approval for cover. Tile to be removed for inspection.
|
INSP-Sprinkler Rough-in | 3/12/2015 | 3/12/2015 | 3/12/2015 | P | PART |
Troy Cobbley
|
|
|
Piping above the new StarBucks is ok to cover. Rough-in passed at the Pharmacy but will need another inspection once the t-bar is installed. 2" line is not connected to the existing main yet.
|
Permit Ready to Issue | | | 3/5/2015 | | DONE |
Christina Prado
|
|
|
|
Issue and Print Permit | | | 3/5/2015 | | DONE |
Christina Prado
|
|
|
|
Inspection Record Card- Fire | 3/5/2015 | | 3/5/2015 | | DONE |
Christina Prado
|
|
|
|
Intake Approval | | | 3/3/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 3/3/2015 | | 3/3/2015 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 3/3/2015 | | 3/3/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 3/3/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/3/2015 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 2/23/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Feb 23 2015 8:48AM
|