INSP-Final Inspection | 6/12/2018 | 6/13/2018 | 6/13/2018 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Sprinkler Rough-in | 8/14/2015 | 8/14/2015 | 8/14/2015 | P | PASS |
Jim Page
|
|
|
Rough to cover inspection passed/complete, approved for cover
|
INSP-Sprinkler Rough-in | 5/13/2015 | 5/14/2015 | 5/14/2015 | P | PASS |
Troy Cobbley
|
|
|
Rough-in passed for the new Conference Room. Piping can be covered.
|
INSP-Final Inspection | 4/28/2015 | 4/28/2015 | 4/29/2015 | P | PART |
Troy Cobbley
|
|
|
Plan modifications will be needed showing the revised layout of the de-mountable walls prior to a final sign off.
|
INSP-Sprinkler Rough-in | 4/20/2015 | 4/20/2015 | 4/20/2015 | P | PASS |
Troy Cobbley
|
|
|
Piping as marked "ok" is ok to cover.
|
Intake Approval | | | 3/18/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 3/18/2015 | | 3/18/2015 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 3/18/2015 | | 3/18/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 3/18/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 3/18/2015 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 3/18/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/18/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/18/2015 | | 3/18/2015 | | DONE |
Brittany Hill
|
|
|
|
Application received | | | 3/17/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 17 2015 2:01PM
|