INSP-Final Inspection | 4/21/2016 | 4/21/2016 | 4/21/2016 | P | PASS |
Jim Page
|
|
|
Final fire alarm inspection passed/complete
|
INSP-Final Inspection | 11/19/2015 | 11/20/2015 | 11/20/2015 | A | PART |
Jim Page
|
|
|
Final inspection for 4th floor alarms passed/complete.
|
INSP-Alarm Testing | 10/14/2015 | 10/14/2015 | 10/14/2015 | A | PART |
Jim Page
|
|
|
Fire alarm inspection for 3rd floor past/complete
|
INSP-Alarm Testing | 6/29/2015 | 6/30/2015 | 6/30/2015 | A | PART |
Jim Page
|
|
|
Inspected/tested horns and strobes, 2nd floor and basement levels, both passed inspection. Activated newly installed pull station 2nd floor and basement level, both reported to fire panel. Tested elevator recall on east elevator, both for 2nd floor as well as basment level, elevator recalled to first floor, west elevator still needs tested for recall, elevator was being serviced at time of inspection.
|
Permit Ready to Issue | | | 3/27/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 3/27/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 3/27/2015 | | 3/27/2015 | | DONE |
Christina Prado
|
|
|
|
Plan assigned to (Lee) | 3/25/2015 | | 3/25/2015 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 3/25/2015 | | FAIL |
|
|
|
See review comments.
|
Miscellaneous action | | | 3/25/2015 | | DONE |
|
|
|
Failed review comments emailed to applicant.
|
Alarm Plan Check | 3/25/2015 | | 3/25/2015 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 3/25/2015 | | DONE |
|
|
|
Resubmittal approved with review comments. Projectdox updated.
|
Application received | | | 3/23/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 23 2015 4:59PM
|