DOC - Permit Finaled | | | 10/20/2015 | | PASS |
|
|
|
*As built plans accepted by plan review.
|
Miscellaneous action | | | 8/10/2015 | | DONE |
|
|
|
As Built drawings received. Uploaded to Projectdox.
|
INSP-Final Inspection | 7/28/2015 | 7/29/2015 | 7/30/2015 | P | PASS |
Troy Cobbley
|
|
|
As-builts have not bee provided yet.
*10/20/15 - As builts accepted by plan reviewer*
|
INSP-Final Inspection | 7/23/2015 | 7/24/2015 | 7/24/2015 | A | FAIL |
Troy Cobbley
|
|
|
Permit will be ok to final when as-builts are received that reflect the additional strobes. Functional testing passed
|
INSP-Final Inspection | 7/22/2015 | 7/23/2015 | 7/23/2015 | A | FAIL |
Troy Cobbley
|
|
|
Missing coverage outside of the Pharmacy, missing strobe in the Pharmacy, overspaced strobe at the Bakery. No testing performed. Will need as-builts if notification is added in Bakery.
|
Miscellaneous action | | | 6/9/2015 | | DONE |
|
|
|
Applicant emailed to find out when drawings will be ready. I verified that tasks wer not complete on the applicants end and informe him that once all were done, I could start the review.
|
Alarm Plan Check | 6/9/2015 | | 6/9/2015 | | PASS |
Lee G Meredith
|
|
|
|
PLANS TAKEN FRONT DESK ALARM | | | 6/9/2015 | | DONE |
|
|
|
Third submittal approved with conditions and review comments. Projectdox updated.
|
Permit Ready to Issue | | | 6/9/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 6/9/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/9/2015 | | 6/9/2015 | | DONE |
Kristal Soland
|
|
|
|
Plan resubmittals received | | | 6/3/2015 | | DONE |
|
|
|
calculations provided.
|
Alarm Plan Check | 5/11/2015 | | 5/11/2015 | | FAIL |
Lee G Meredith
|
|
|
Calculations not provided. Review comments emailed to applicant.
|
Plan resubmittals received | | | 5/8/2015 | | DONE |
|
|
|
|
Application received | | | 3/26/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Mar 26 2015 10:01AM
|
Plan assigned to (Lee) | 3/26/2015 | | 3/26/2015 | | DONE |
Lee G Meredith
|
|
|
|
1st review completed | | | 3/26/2015 | | FAIL |
|
|
|
See 1st alarm review comments.
|