INSP-Final Inspection | 10/12/2015 | 10/13/2015 | 10/13/2015 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 8/12/2015 | 8/12/2015 | 8/12/2015 | P | PASS |
Troy Cobbley
|
|
|
Overhead hydro test passed
|
INSP-Supply line flush | 7/28/2015 | 7/29/2015 | 7/29/2015 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed
|
INSP-Sprinkler Rough-in | 6/19/2015 | 6/22/2015 | 6/22/2015 | A | PASS |
Troy Cobbley
|
|
|
Underground supply line cover passed.
|
Intake Approval | | | 4/15/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 4/15/2015 | | 4/15/2015 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 4/15/2015 | | 4/15/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 4/15/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/15/2015 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 4/15/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 4/15/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 4/15/2015 | | 4/15/2015 | | DONE |
Brittany Hill
|
|
|
|
Application received | | | 4/8/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 8 2015 5:13PM
|