INSP-Final Inspection | 10/26/2016 | 10/28/2016 | 10/27/2016 | P | PASS |
Jim Page
|
|
|
Final underground inspection passed/complete
|
INSP-Sprinkler Rough-in/Hydro | 2/18/2016 | 2/19/2016 | 2/19/2016 | P | PASS |
Jim Page
|
|
|
hydrostatic test (200psi for 2 hours) passed/complete for underground fire supply main.
|
INSP-Supply line flush | 2/16/2016 | 2/16/2016 | 2/17/2016 | P | CANC |
Jim Page
|
|
|
Inspection request cancelled, assigned to wrong inspector.
|
INSP-Supply line flush | 2/16/2016 | 2/16/2016 | 2/16/2016 | P | DONE |
Jim Page
|
|
|
Underground fire main flush complete.
|
INSP-Supply line flush | 2/12/2016 | 2/16/2016 | 2/15/2016 | A | CANC |
Jim Page
|
|
|
Suez was contacted to turn the water on at the site on Monday morning. Please contact Matt with questions. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 6/3/2015 | 6/4/2015 | 6/4/2015 | P | PASS |
Jim Page
|
|
|
Underground approved for cover.
|
INSP-Sprinkler Rough-in | 6/2/2015 | 6/3/2015 | 6/3/2015 | A | CANC |
Jim Page
|
|
|
This is an underground to cover inspection. Bryan is the contact. Thanks. Phone #: ###-#### >> Inspection requested via web by Stan Beus Inspection cancelled from web by: Stan Beus
|
Intake Approval | | | 4/17/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 4/17/2015 | | 4/17/2015 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 4/17/2015 | | 4/17/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 4/17/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/17/2015 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 4/17/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 4/17/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 4/17/2015 | | 4/17/2015 | | DONE |
Brittany Hill
|
|
|
|
Application received | | | 4/16/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 16 2015 1:17PM
|