INSP-Final Inspection | 7/10/2015 | 7/10/2015 | 7/10/2015 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection passed/complete
|
INSP-Sprinkler Rough-in | 6/25/2015 | 6/26/2015 | 6/26/2015 | A | PASS |
Jim Page
|
|
|
2nd floor rough-in inspection passed/complete, approved for cover
|
Permit Ready to Issue | | | 6/24/2015 | | DONE |
|
|
|
all requirments met
|
Issue and Print Permit | | | 6/24/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 6/24/2015 | | 6/24/2015 | | DONE |
Carlos Velazquez
|
|
|
|
Alarm Plan Check | 6/23/2015 | | 6/23/2015 | | PASS |
Lee G Meredith
|
|
|
Plans approved as previously noted by Tim Frost. Detection portion has been approved with FIR15-00423.
|
PLANS TAKEN FRONT DESK ALARM | | | 6/23/2015 | | DONE |
|
|
|
Plans approved as noted by Tim Frost.
|
Miscellaneous action | | | 5/7/2015 | | PEND |
|
|
|
Project documents are all fine but cannot be approved until the detection portion of the preaction system is submitted. Therefore, the project is on hold.
|
Early Start | | | 5/7/2015 | | PASS |
|
|
|
See Document
|
Sprinkler Plan Check | 5/4/2015 | | 5/4/2015 | | FAIL |
Tim Frost
|
|
|
|
1st review completed | | | 5/4/2015 | | FAIL |
Tim Frost
|
|
|
|
Miscellaneous action | | | 5/4/2015 | | DONE |
Tim Frost
|
|
|
Emailed contractor in regards to failed review.
|
Intake Approval | | | 5/1/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 5/1/2015 | | 5/1/2015 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 4/27/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 27 2015 10:23AM
|