INSP-Final Inspection | 5/11/2015 | 5/12/2015 | 5/14/2015 | P | PASS |
Katie Marron
|
|
|
Scope of work completed satisfactory. Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 5/1/2015 | 5/1/2015 | 5/1/2015 | P | PART |
Katie Marron
|
|
|
Rough-in inspection pass. Ok to cover soffit.
|
INSP-Sprinkler Rough-in | 4/30/2015 | 4/30/2015 | 4/30/2015 | P | FAIL |
Katie Marron
|
|
|
Soffit with two new pendants was fully enclosed, and pipe drops was not able to be seen. Contractor to expose pipes and reschedule.
|
Intake Approval | | | 4/28/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 4/28/2015 | | 4/28/2015 | | DONE |
Tim Frost
|
|
|
|
Sprinkler Plan Check | 4/28/2015 | | 4/28/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 4/28/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/28/2015 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 4/28/2015 | | DONE |
|
|
|
|
Issue and Print Permit | | | 4/28/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 4/28/2015 | | 4/28/2015 | | DONE |
Brittany Hill
|
|
|
|
Application received | | | 4/27/2015 | | DONE |
|
|
|
Application submitted via PDS Online on Apr 27 2015 2:10PM
|