INSP-Final Inspection | 5/25/2015 | 5/26/2015 | 5/26/2015 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 5/25/2015 | 5/26/2015 | 5/26/2015 | A | PASS |
Troy Cobbley
|
|
|
Overhead hydro and rough-in passed
|
INSP-Final Inspection | 5/20/2015 | 5/22/2015 | 5/22/2015 | P | CANC |
Troy Cobbley
|
|
|
To be rescheduled for next week
|
INSP-Sprinkler Rough-in/Hydro | 5/20/2015 | 5/21/2015 | 5/22/2015 | P | CANC |
Troy Cobbley
|
|
|
To be rescheduled for next week
|
Sprinkler Plan Check | 5/8/2015 | | 5/8/2015 | | PASS |
Tim Frost
|
|
|
Please, see attached comments.
|
1st review completed | | | 5/8/2015 | | PASS |
Tim Frost
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 5/8/2015 | | DONE |
Tim Frost
|
|
|
|
Permit Ready to Issue | | | 5/8/2015 | | DONE |
|
|
|
all requirments met
|
Issue and Print Permit | | | 5/8/2015 | | DONE |
|
|
|
|
Inspection Record Card- Fire | 5/8/2015 | | 5/8/2015 | | DONE |
Carlos Velazquez
|
|
|
|
Intake Approval | | | 5/7/2015 | | PASS |
|
|
|
|
Plan assigned to (Tim) | 5/7/2015 | | 5/7/2015 | | DONE |
Tim Frost
|
|
|
|
Application received | | | 5/4/2015 | | DONE |
|
|
|
Application submitted via PDS Online on May 4 2015 5:33PM
|